Skip to content

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Related FAQs

VIDEO: Can trade credit insurance help to keep the supply chain moving?

On Tuesday 23rd June, partner Emma Digby was in conversation with Steve Hamstead and Mark Smith from AON along with Ward Hadaway commercial lawyer Nathan Bilton in a webinar titled Can trade credit insurance help to keep the supply chain moving?

The insurance market is under untold pressure as a result of the pandemic, and in such times there is a risk that insurers will cancel or reduce credit lines, particularly in certain high risk sectors such as retail. However the Government has stepped in to effectively underwrite the existing trade credit insurance agreements, and to keep trade supplies moving. Will this be enough?

In this webinar, we discussed:

  • the Government backed scheme and how it will operate
  • the prospects of obtaining insurance going forward, and whether it will become too cost prohibitive
  • could the new legislation put your business at risk and jeopardise your insurance cover if you cannot cancel a contract when you are not getting paid for your goods or services
  • the Brexit effect, and how this will affect the insurance market
  • protecting your business with proper risk assessment processes and paperwork
What can suppliers of goods and services do to minimize risk?

If suppliers still wish to terminate the contract, they must contact the directors or the officeholder dealing with the insolvency process and obtain their approval to terminate the contract – which, of course, might not be given.

If the continued obligation under the contract to supply goods/services to the customer would place the supplier in financial hardship the supplier can apply to court for permission to terminate the contract.  This will involve time and legal expense.

Which products and services are affected?

Initially, the relaxation applied to supermarkets and food suppliers. This was subsequently widened to apply to other businesses, permitting them to collaborate where necessary to respond to the crisis in the interests of consumers.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Can I still have my domestic gas appliances tested during the coronavirus outbreak?

Yes. The Health and Safety Executive has stated (as quoted from the Gas safe register site):

“Landlords have a legal duty to repair and maintain gas pipework, flues and appliances in a safe condition, to ensure an annual gas safety check on each appliance and flue, and to keep a record of each safety check.

“If you anticipate difficulties in gaining access as the Covid-19 situation progresses, you have the flexibility to carry out annual gas safety checks two months before the deadline date. Landlords can have the annual gas safety checks at their properties carried out any time from 10 to 12 calendar months after the previous check and still retain the original deadline date as if the check had been carried out exactly 12 months after the previous check.

“You are encouraged to arrange your annual gas safety checks as early as possible, as a contingency against tenants being in self-isolation for 14 days (in line with current guidelines), or gas engineers being unavailable due to illness. The two-month period to carry out annual gas safety checks should provide adequate resilience in most situations.

“In the event you are unable to gain access to the property, e.g. persistent refusal of access due to vulnerable tenants self-isolating, you will be expected to be able to demonstrate that you took reasonable steps to comply with the law, and that you are seeking to arrange the safety check as soon as all parties are able. This will need to include records of communication with the tenant, and details of your engineers attempts to gain access.”

Many Registered Providers have been suspending all gas and electrical testing where internal access is required, continuing checks in communal areas and are carrying out emergency repairs only, whilst void works are suspended and staff are working from home. This does not comply with the legislation, or the guidance.