Skip to content

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Related FAQs

What guidance has the CMA issued about how it expects businesses to behave in response to the global pandemic?

On 30th April 2020, the CMA issued a guidance note setting out its views about how the law operates in relation to refunds.

Where a contract is not performed as agreed, the CMA considers that in most cases, consumer protection law will generally allow consumers to obtain a refund.

This includes the following situations:

  • Where a business has cancelled a contract without providing any of the promised goods or services
  • Where no service is provided by a business, for example because this is prevented by Government public health measures
  • A consumer cancels, or is prevented from receiving any services, because Government public health measures mean they are not allowed to use the services.

In the CMA’s view, this will usually apply even where the consumer has paid what the business says is a non-refundable deposit or advance payment.

This positon reflects the CMA’s previous guidance which they had issued in relation to the requirement of fairness in consumer contracts under the Consumer Rights Act 2015, which was that a clause in a contract that gives a blanket entitlement to a trader to cancel a contract and retain deposits paid is likely to be unfair, and therefore unenforceable – it would be unfair to a consumer to lose their deposit if the contract is terminated without any fault on their part, and if they had received no benefit for the payments made.

The CMA’s latest guidance therefore confirms their view that the Covid-19 outbreak does not change the basic rights of the consumer, and that they should not have to pay for goods or services that they do not receive.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What are the standard holiday rules?

Under usual rules, workers are entitled to a minimum of 28 days holiday including bank holidays, each year. Except in limited circumstances, it cannot be carried between leave years meaning that workers lose their holiday if they do not take it.

The government passed emergency legislation relaxing the carry-over of the 20 days leave entitlement provided under EU law. Where it is not reasonably practicable for an employee to take leave in the relevant leave year as a result of the effects of the coronavirus then they could be entitled to carry over the untaken leave into the next year.

Does Force Majeure apply to the leasing of commercial property?

Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.

I have essential workers who do home visits. How do I assess the risks?

The fundamentals of risk assessment remain the same as for any other foreseeable risk.

Focus on risk controls which reflect Government guidance; social distancing (2 metres) and avoiding contact with occupiers if possible, high-quality PPE – disposable overalls, gloves and fluid repellent surgical face masks, ready access to antibacterial wipes for surfaces, tools and equipment and plentiful hand sanitizer.