Skip to content

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Related FAQs

What should I do if I think this is relevant to my contracts?

It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:

  • Ensure that initial contact with your counterparty is framed in the correct way
  • Ensure that any variations are fully documented so that both parties are fully protected
What is the "Job Retention Bonus"?

As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
What are the changes to the law?

On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process.  This has very important consequences for many businesses as it could expose them to greater financial risks.

Freedom to Speak up – a reminder

Has there ever been a more important time for all staff to feel that they are able to raise concerns about their working environment?

It is a pertinent time to remind all staff that they should be able to raise concerns without the fear of repercussions. It is a good time to be reviewing and re-issuing your Freedom to Speak up/Whistleblowing policy to all. Likewise it is a good time to remind all staff that they should not treat others unfairly or detrimentally for raising health and safety concerns.

Both subjecting someone to a detriment because they have blown the whistle or raised health and safety concerns (and dismissing someone for the same) is unlawful.