Skip to content

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Related FAQs

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

What happens if a patient is admitted to hospital during the pandemic?
What allowances has the Government proposed for company meetings?

The Government’s Corporate Insolvency and Governance Act introduces amendments to the current rules for companies on holding meetings, to address the difficulties companies are facing due to the Covid-19 pandemic.

The new provisions apply to meetings held between 26 March 2020 and 30 September 2020 (referred to as the “Relevant Period”). Subsequent regulations by the Government can be used to shorten this period or extend by up to 3 months but not past 5 April 2021.

The provisions will have retrospective effect, so meetings that were held after 26 March 2020 that may not have met the usual legal requirements due to lockdown, will be validated under these new provisions. These provisions under the Act make amends to relevant legislation and override a company’s articles of association.

For general meetings and certain other meetings of companies, the Act states that:

  • The meeting need not be held in any particular place;
  • The meeting may be held, and any votes may be cast, by electronic means or other means;
  • The meeting may be held without anyone being in the same place
  • Persons attending the meeting no longer have the following rights: the right to attend in person, the right to participate in the meeting other than by voting, or the right to vote by particular means.

The aim of these changes is to facilitate virtual meetings, and remove the need for a physical venue.

Where a company was required to hold its AGM between 26 March and 30 September 2020, it can be held at any time before 30 September 2020.  The Secretary of State has the power to make regulations to further extend the deadline.

What should I do if I think this is relevant to my contracts?

It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:

  • Ensure that initial contact with your counterparty is framed in the correct way
  • Ensure that any variations are fully documented so that both parties are fully protected
What are the consequences of the shake up of the planning Use Class system?

The Town and Country Planning (Use Classes) (Amendment) (England Regulations) 2020 were laid before Parliament and come into force on 1 September 2020. They apply in England only.

The changes include the revocation of the following Use Classes;

  • A1 – shops
  • A2 – financial and professional services
  • A3 – restaurants and cafes
  • A4 – drinking establishments
  • A5 – hot food takeaways
  • B1 – business. Also revoked are the sub parts of B1;
    • B1(a) – offices
    • B1(b) – research and development of products and processes
    • B1(c ) – industrial process
  • D1 – non residential institutions
  • D2 – assembly and leisure

The changes include the amendment of the following Use Class;

  • B2 (industry)

The changes include the introduction of the following Use Classes;

  • E – commercial, business and service
  • F.1 – learning and non-residential institutions
  • F.2 – Local community

There are no changes to the following Use Classes;

  • C1 – hotels, boarding and guest houses
  • C2 – residential institutions
  • C3 – dwellinghouses
  • C4 – small HMO

From 1 September 2020;

  • Small retail shops (not more than 280 sq metres net sales area) selling essential goods including food and at least 1 kilometre from another shop will cease being an A1 use and will become a F.2 (local community) use;
  • Other A1 shops will become an E (commercial, business and service) use;
  • A2 uses will become an E (commercial, business and service) use;
  • A3 uses will become an E (commercial, business and service) use;
  • A4 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
  • A5 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
  • B1 uses (included B1(a), B1 (b) and B1 (c) will become an E (commercial, business and service) use;
  • B2 uses will either be B2 uses or will be Class E uses.
  • Clinics, health centres, creches, day nurseries and day centres (previously D1 uses) will become an E (commercial, business and service) use;
  • Schools, non residential education and training centres, museums, public libraries, public halls, exhibition halls, places of worship, law courts (previously D1 uses) will become an F.1 ( learning and non-residential institutions) use;
  • Cinemas, concert halls, live music performance venues, bingo halls and dance halls (previously D2 uses) and will be sui generis, ie not in any use class;
  • Gyms, indoor sport, recreation or fitness not involving motorised vehicles or firearms principally to visiting members of the public (previously D2 uses) will become an E (commercial, business and service) use;
  • Hall or meeting place for the principal use of the local community (previously D2 uses) will become an F.2 (local community) use;
  • Indoor or outdoor swimming baths, skating rinks, outdoor sports or recreation grounds (not involving motorised vehicles or firearms) (previously D2 uses) will become an F.2 (local community) use.

Changes of use within a Use Class do not constitute development. That being the case, provided the Order is applicable, its operation not having been restricted by planning condition, Agreement or Article 4 (1) Direction for example, planning permission would not be required, development as defined not happening.  If legally binding confirmation is required that planning permission is not required this can only be obtained by way of a successful application for a Certificate of Lawfulness. In the absence of such, there is some risk.

It remains the case that planning permission may be required for operational works to buildings. It also remains the case that other consents and permissions may be necessary for example licenses. Furthermore amendments to leases may be required if the property is rented.

The Regulations additionally include transitional arrangements because of permitted development rights for changes of use in the Town and Country Planning (General Permitted Development) (England) Order amongst others.  To respond to this Regulations introduce a ‘material period’ which is defined as meaning the period beginning 1 September 2020 and ending 31 July 2021. It is expected during the material period the Orders giving permitted development rights for changes for use which do constitute development will be amended / updated to reflect the new use classes.

Click here to view the Regulations.

The above is based on our understanding of the new Regulations at the time of issue and in advance of planning practice guidance being issued.