Skip to content

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Related FAQs

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What can suppliers of goods and services do to minimize risk?

If suppliers still wish to terminate the contract, they must contact the directors or the officeholder dealing with the insolvency process and obtain their approval to terminate the contract – which, of course, might not be given.

If the continued obligation under the contract to supply goods/services to the customer would place the supplier in financial hardship the supplier can apply to court for permission to terminate the contract.  This will involve time and legal expense.

What does information and consultation involve?

There are two stages:

  • Stage 1 – The provision of written information to the representatives.
  • Stage 2 – Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters

Stage 1: Provision of information

The first stage in the collective consultation process is to provide the representatives with written information including details of the proposed redundancies (often called a section 188 letter). This information must be given to the appropriate representatives and the time limit before dismissals can take effect does not start to run until they have received it. It is this information which ‘starts the clock’.

It is possible that there will be changes to the proposals during the consultation process: indeed that is part of the reason for the process. The employer’s obligation is not just to provide the appropriate representatives with the relevant information at the start of the process. It is under a continuing obligation to provide them with information in writing about any developments during the consultation process (although later changes do not ‘restart the clock’ before dismissals can take effect).

Stage 2: Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters

The consultation process must include consultation “with a view to reaching agreement with the appropriate representatives” on ways of:

  • Avoiding the dismissals
  • Reducing the number of employees to be dismissed
  • Mitigating the consequences of the dismissals
When does IR35 generally apply?

It would apply if the contractor uses an intermediary to provide their services or labour and they would be deemed to be an employee or office holder for tax purposes if they were hired directly by the end user client rather than via the intermediary PSC. This would of course require an assessment of employment status for tax purposes.

Contractors who are not taxed in the UK and supply their services exclusively from outside of the UK are unaffected.

If IR35 applies, tax and NIC’s should be deducted under PAYE by the PSC. In reality this has not been happening so a major reform of the regime was due to be implemented in April 2020. The changes were postponed by one year and are due to take effect from 6 April 2021.

“Within IR35” means a contractor arrangement is caught by IR35 and the individual should be taxed as an employee.

“Outside IR35” means a contractor arrangement is not caught by IR35 and the contractor status is fine.

What are the responsibilities of employers under the coronavirus Test and Trace scheme?

The Government has produced workplace guidance for employers, setting out 2 key messages for employers:

  • Continue to make workplaces as safe as possible; and
  • Encourage workers to heed any notifications to self-isolate and to support them while they are require to isolate

Government guidance can be accessed here: How it works (an overview) and Workplace guidance for employers.