What should I do if the contractor is in suspected financial difficulty?
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
Related FAQs
Maintenance Orders embodied in a Court Order are variable. If you have lost a very large part of your income, then the Courts ought to take that into consideration when looking at a Court Application to reduce or end spousal maintenance payments. The outcome of any Court Application will, however, depend on a number of factors.
Technically, you should not just stop paying or reduce the maintenance payments, as your ex-spouse could then make an Application to Court for enforcement and payment of the arrears. You could ask the Court to forego you having to pay those arrears if you had evidence to prove that you could not make the payments, however, the Court will need to take a fair approach and you should not assume this request will be agreed.
You should first try to negotiate a reduction or termination of the maintenance with your ex-spouse, either directly or through a Solicitor. If this is possible, you should obtain a Court Order reflecting that agreement. Where a sensible compromise cannot be reached, a Court Application may be necessary.
You will claim a pro rata’d amount of 80% of salary, based on the proportion of hours not worked out of the employee’s normal working hours (their “usual” hours).
There are 2 ways to calculate an employee’s usual hours, depending on whether they have fixed or variable hours/pay:
- For those with fixed hours/pay, you take the number of hours worked in the pay period before 19 March 2020.
- For those with variable hours/pay, you take the higher of:
- the average number of hours worked in the tax year 2019 to 2020 or
- the corresponding calendar period in the tax year 2019 to 2020.
If employees are paid per task or piece of work done, you should work out the usual hours for these employees in the same way as for other employees who work variable hours, if possible.
When you calculate the usual hours, you should include any hours of leave for which they were paid their full contracted rate (such as annual leave) and any hours worked as overtime (but only if the pay for those hours was not discretionary).
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Yes, but your claim will be limited to any enhanced contractual payments you make to employees who qualify for the relevant family related pay.
All maternity and parental rights remain in force for anyone in this category who is furloughed. However you may need to calculate average weekly pay differently if the employee was furloughed and then started family related leave on or after 25 April 2020.
Furlough pay cannot be claimed for the period that an employee is receiving Maternity Allowance. An employee can agree to accept furlough pay but they must contact Jobcentre Plus to stop their Maternity Allowance payments for this period.
We have developed a toolkit to assist with compliance. The Toolkit contains a specimen contract; detailed guidance; step by step guides and flowcharts; details of the factors to take into account for the status determination test; procedures for challenging the determination; and standard letters for the process. Click here to fill in a form and register your interest in the Toolkit, which contains:
- Detailed guidance in the form of Key Facts
- Employment status checklist
- Employment status assessment flowchart
- Status questionnaire and guidance
- Letter confirming self-employed status (agency)
- Letter confirming employed status (agency)
- Letter confirming self-employed status (direct with PSC)
- Letter confirming employed status (direct with PSC)
- Status disagreement process guidance
- Status disagreement process flowchart
- Letter confirming outcome of status disagreement process
- Consultancy agreement