What should I do if the contractor is in suspected financial difficulty?
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
Related FAQs
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Some examples of the key questions to ask include:
- Is there still a viable underlying business that is likely to continue beyond the current crisis?
- What does the revised short to medium cash flow look like and will the company continue to be able to pay its liabilities?
- Does the company have the support of all of its stakeholders – lenders, shareholders, customers, suppliers and banks – even though the business might be in breach of its own obligations?
- What measures could (and should) the board put in place to protect creditors, including making sure that exposure to creditors (both collectively and individually) is not increased, assets are not sold at less than value and no creditor is treated more favourably than another?
- Is there still a reasonable prospect of the business avoiding liquidation or administration?
The key question is always whether accepting the money is in the best interests of creditors as a whole bearing in mind that accepting Government support and continuing to trade might increase the company’s overall liabilities. Directors should be mindful that if the business fails, their decisions during this critical time may be scrutinised and it is therefore important that directors have up-to-date financial information and projections to form the basis of any decisions, take stock, get the right advice and document the decisions that are taken.
It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:
- Ensure that initial contact with your counterparty is framed in the correct way
- Ensure that any variations are fully documented so that both parties are fully protected
You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.
If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.
Records of disputed determinations and the outcome of any appeal should be kept.
This scheme is specifically aimed at creating jobs for 18-24 year olds who are on Universal Credit and considered most at risk of unemployment because of the economic downturn. The Government has announced that it will pay young people’s wages (equivalent to 100% the National Minimum Wage plus the associated National Insurance contributions and employer minimum automatic enrolment contributions) for up to 6 months, and that this will amount to a grant worth approximately £6,500 per young person.
The jobs that are created must provide a minimum of 25 hours per week and be paid at a minimum of the National Minimum Wage The Chancellor announced that will be no cap on the number of jobs that will be funded under the Kickstart scheme.