Skip to content

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements

Related FAQs

What can suppliers of goods and services do to minimize risk?

If suppliers still wish to terminate the contract, they must contact the directors or the officeholder dealing with the insolvency process and obtain their approval to terminate the contract – which, of course, might not be given.

If the continued obligation under the contract to supply goods/services to the customer would place the supplier in financial hardship the supplier can apply to court for permission to terminate the contract.  This will involve time and legal expense.

What happens if an employee refuses to attend work because they are afraid of being exposed to COVID-19 particularly the new more transmissible strain?

An employee can refuse to attend work but their refusal to do so will have to be based on a reasonable belief that their health and safety is in danger.  Whether or not their refusal is reasonable will take into consideration factors such as the employee’s own health and whether they are at a higher risk of becoming seriously ill if they contract Covid-19 and the steps their employer has out in place to mitigate the danger of contracting Covid-19 at work.

In such circumstances where the employee’s belief is deemed to be reasonable, they will be entitled to stay at home and receive full pay.

If an employee is subsequently dismissed for refusing to attend work in these circumstances, they may be able to bring a claim for unfair dismissal.

Do the usual publicity requirements for planning applications still apply?

The Government has introduced new regulations, which took effect on 14 May 2020, to relax the publicity requirements in respect of planning applications.

Planning applications are usually required to be publicised by way of site notices and local newspaper notices and applications are to be made available for public inspection. The Government has recognised that these actions may not always be possible in accordance with social distancing guidelines and in order that Councils do not delay applications as a result of an inability to comply with the publicity requirements, the Government has relaxed the requirements.

A Local Planning Authority is now required to “take reasonable steps” to publicise a planning application, which may be through use of online newspapers, social media, or other electronic measures. What is considered reasonable will depend upon the circumstances of an individual application and will be proportionate to the scale and impact of the development. A large development that has previously generated significant interest will require more steps to bring the application to the attention of all of those with an interest than a householder application. The guidance emphasises the role of the publicity requirements, namely to enable those with an interest to make representations and to effectively participate in the decision making process and therefore community engagement remains key. It is recommended that the officer’s report refers to the steps taken where a Council has relied upon the temporary publicity arrangements.

The requirement to make planning applications available for public inspection has also been temporarily suspended providing that the applications are available for online inspection. In reality most LPAs already provide such an online facility. Where individuals are unable to access an application online LPAs should make alternative arrangements, for example providing information over the phone or providing a hard copy set of documents by post.

The regulations however only amend the statutory publicity requirements. In addition to these, all LPAs are required to have a Statement of Community Involvement which may provide for additional publicity requirements and the LPA will be bound by these regardless of the temporary relaxation of any statutory requirements. Where a Statement of Community Involvement does go beyond the statutory requirements, the Government guidance suggests that LPAs update these to ensure that local communities can continue to be consulted in the current climate.

The regulations are currently due to expire on 31 December 2020.

I’m a social housing provider. What do I do if I know my tenants are flouting the social distancing guidelines?

If a tenant continues to refuse to take heed of the government’s social-distancing guidelines, for example by inviting large groups of people who do not reside there to their property, it can constitute a nuisance. One housing association successfully applied for an injunction. The injunction ordered by the Court stipulated that no persons, other than the children of the tenant, are to attend the property until the current social-distancing restrictions are lifted by the government.

A representative of the housing association highlighted the need for the current guidelines to be followed and the need for housing providers to ensure that all residents living in their communities are kept safe during this time of ‘unprecedented risk’.

This case demonstrates that flouting of the current restrictions is likely to be considered anti-social in the eyes of the courts – a point which all housing providers should bear in mind during this period. Further, it highlights the availability of an alternative remedy to the issuing of possession proceedings (in light of the government’s moratorium on evictions) to deal with anti-social behaviour during the next three months, Covid-19 related or not.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?