What should an employer do when an employee has been told to self-isolate under the coronavirus Test and Trace scheme?
- Do not require them to work
- Continue to communicate with and support them
- Allow them to work from home, is there alternative work for them to do if they can’t do their work from home
- Offer SSP or allow them to take holiday if they want to.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
It has also been proposed in the Corporate Insolvency and Governance Bill that public companies who were due to file their accounts in the period from 26 March 2020 to 30 September 2020 will have until the earlier of the 30 September 2020 and the date which is 12 months after the end of their relevant accounting period to do this.
This is separate from the pre-existing scheme, announced on 25 March 2020, whereby companies can apply to Companies House for a 3 month extension for filing their accounts.
The changes will not apply to end users who are a small company. If you meet two out the following 3 conditions, you will meet the small company definition and are therefore exempt from the changes to IR35:
- Annual turnover is no more than £10.2 million
- Balance sheet total is no more than £5.1 million
- No more than 50 employees
Companies will always be classified as small in their first financial year. Public companies will always be considered to be medium or large businesses and cannot fall under this exemption.
For a group company to be a small company its parent company must also meet the small company definition.
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Again, the primary point must be that an open dialogue is held with that individual to understand their concerns and to properly consider the impact that not wearing PPE will have on their abilities to undertake their duties. Consideration must be given as to whether there are any parts of their duties that they can undertake and whether they can remain in their role. Engage with the individual to ensure that you understand their point of view. What other duties can they do if they cannot do fulfil all the duties of their role?