What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Related FAQs
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Overall it is our experience that the Courts are quickly adapting in the context of the Coronavirus epidemic and making pragmatic decisions. The Judges seem live to the difficulties currently been faced by practitioners dealing with litigation and they are applying the new guidance.
The Courts are also mindful of pressures on NHS frontline staff and are taking steps not to put additional pressures on them at this time, including in our experience vacating an imminent Trial.
Specialist healthcare lawyers from Ward Hadaway ran a free webinar looking at the practical and legal considerations if required to treat healthcare workers from a BAME background or other vulnerable groups differently in the fight against the Covid-19 pandemic.
As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.
If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.
If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.
Yes. Government guidance now confirms that employers can be required to take holiday during a period of furlough, so long as they are given minimum notice to do so. The notice required is double the length of the holiday.
Employers are also able to cancel employees’ holidays (or require them not to take holiday) if they are on furlough, for example if they are not in a position to pay the additional 20% top up to their normal wages (or more where they earn in excess of the £2,500 monthly cap on furlough payments). Again, employers are required to provide a minimum period of notice of cancellation, which in this case, is the length of the planned holiday.
Employers can ask employees to take or cancel holiday with less notice but they would need to get their agreement to do so.
Government guidance has been updated to state that “Employees should not be placed on furlough for a period simply because they are on holiday for that period.” If a period of furlough happens to coincide with an employee’s holiday then you should ensure that there are business grounds to support furlough being used in that instance so that it isn’t just being used as a means to fund holiday utilisation.