What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Related FAQs
It is envisaged that employees of organisations falling into the first two categories set out above and won’t be eligible for the job retention scheme in relation to the majority of their employees. It is envisaged that NHS Trusts for example are going to require their staff to be working at full capacity where possible. However, the guidance doesn’t definitely exclude public sector organisations from furloughing employees and notably the government expects such organisations to use public money to continue to pay staff and not furlough them, rather than say requires. In reality, it is difficult to see how such an organisation will be able to rely on the scheme, but the guidance doesn’t completely rule it out.
If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:
- The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
- The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
- The contractor should have sufficient control over how, when and where (if possible) they provide the services;
- A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task
We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Hosted by NewcastleGateshead Initiative, Partners Damien Charlton and Jane Garvin discussed in this webinar contracts, managing supply chains and the role of directors, with a particular focus on cancellation of events and businesses in the tourism and hospitality sector.
You can find a recording of the webinar from NGI here.
The General Medical Council (GMC) have published guidance online for doctors during this time of uncertainty.
Alongside this, their website displays guidance for temporary registration to approximately 15,000 doctors, who left the register or gave up their licence to practise in the last three years.
These clinicians have been contacted to assist with the growing pandemic, outlining the process they would follow and informing them of their right to opt-out. The Secretary of State for Health can ask the GMC to grant such registration under Section 18a of the Medical Act 1983, in an emergency.