Skip to content

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

Related FAQs

Are permitted development rights now in existence for the creation of emergency medical facilities?

Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:

  • Preventing an emergency
  • Reducing, controlling or mitigating the effects of an emergency
  • Taking other action in connection with an emergency

It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.

The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.

Further detail of the permitted development right is available at the link below.

http://www.legislation.gov.uk/uksi/2020/412/made

Can I switch an existing loan facility onto the CBILS scheme?

If a business has been provided with a loan from 23 March on commercial terms, providing the borrower meets the CBILS eligibility criteria, lenders have been asked to bring these facilities onto CBILS wherever possible (e.g. where the lender is accredited to offer the same facility through CBILS) and changes retrospectively applied as necessary. Please contact us if this applies to you and we can review facilities and advise upon the potential changes that may be made retrospectively to the benefit of the business.

Can I use my Business Interruption insurance to make a claim?

The FCA’s test case in the Supreme Court ruled overwhelmingly in favour of policyholders.  However, business interruption cover generally has the prerequisite of physical damage or loss to the property (or in some circumstances, the presence of a notifiable disease at the property or within a certain radius of it), to recover losses caused by the interruption to your business. The onus is on insurers to re-assess those claims which are impacted by the Supreme Court’s judgment and to make contact with the policyholders regarding next steps. If you have not already made a claim, in the first instance the terms of any policy should be checked carefully to see whether business interruption cover is provided.

What support is provided by the government under CBILS?

The Government will provide the lender with a partial guarantee (80%) against the outstanding facility balance, subject to an overall cap per lender. Note, the Government guarantee is to the lender only, the borrower will always remain 100% liable for the debt.

We understand that will make an initial claim for recovery against the borrower and will, once its normal recovery procedures have been completed, claim against the Government guarantee.

What security will be required for CBILS?

At the discretion of the lender, the Scheme may be used for unsecured lending for facilities of £250,000 and under.

Lenders were required to demonstrate lending additionality (i.e. lending that without the Scheme, wouldn’t have otherwise taken place). The Scheme has been extended to those businesses who would have previously met requirements for a commercial facility and would not have been eligible for CBILS.  As a result  it is suggested that all viable small businesses affected by Covid-19, and not just those unable to secure regular commercial financing, will now be eligible should they need finance to keep operating.

Primary Residential Property cannot be taken as Security under the Scheme. If the lender can offer finance on normal commercial terms without the need to make use of the Scheme, they will do so.