Skip to content

What impact does the Regulations have in respect of matters which arise from Fire Safety Audits – e.g. if balconies with wooden/decking elements are now considered higher risk and whether that would fall to developer to remedy the materials used to construct balconies?

The duty would fall on the owner of the building to control the hazards presented by balconies made from combustible materials. There may be scope (via warranties/indemnities or other terms) arising from the contract between the developer and owner for the owner to seek to recover the cost of remedial works.

Related FAQs

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

What is the position if my turnover is more than £45 million?

With the exception of the Covid-19 Corporate Financing Facility (see below), there was initially little dedicated financial assistance for medium-sized and larger businesses affected by the coronavirus outbreak (the so-called “stranded middle”); however, from 20 April 2020 such businesses (with a turnover above £45 million) have been able to access finance via the Coronavirus Large Business Interruption Loan Scheme (“CLBILS“).

CLBILS operates in a similar manner to CBILS except that a lender can provide:

  • up to £25 million to businesses with turnover from £45 million up to £250 million; and
  • up to £50 million to businesses for those with a turnover of over £250 million.

Finance is available in the form of:

  • term loans
  • revolving credit facilities (including overdrafts)
  • invoice finance and
  • asset finance,

in each case available on repayment terms of up to three years.

Several changes to CLBILS took effect from 26 May 2020. The maximum amount available through CLBILS to a borrower and its group increased from £50m to £200m. Term loans and revolving credit facilities over £50m will be offered by CLBILS lenders which have secured additional accreditation. The maximum size for invoice finance and asset finance facilities remains at £50m. Companies borrowing more than £50m through CLBILS will be subject to further restrictions on dividend payments, senior pay and share buy-backs during the period of the loan. Further information on the most recent changes, including new provisions on seniority of CLBILS facilities, can be found on the CLBILS page on the British Business Bank website. There is also an in-depth FAQs section for businesses, which has the full details of the changes to the scheme.

Unlike CBILS, the UK government will not make payments to cover the interest and any lender-levied fees in the first 12 months of any facility so these larger businesses will not benefit from the no upfront costs and lower initial repayments that smaller businesses eligible for CBILS benefit from. The other key provisions of CLBILS, such as the eligibility criteria, the 80% government-backed guarantee and security, are similar to those of CBILS.

Eligibility is similar to CBILS and businesses must:

  • Be UK-based in its business activity
  • Have an annual turnover of more than £45 million
  • Have a borrowing proposal which the lender would consider viable, were it not for the current pandemic, and for which the lender believes the provision of finance will enable the business to trade out of any short-term to medium-term difficulty
  • Self-certify that it has been adversely impacted by the coronavirus (COVID-19)
  • Not have received a facility under the Bank of England’s Covid Corporate Financing Facility.

Businesses from any sector can apply, except the following:

  • Credit institutions (falling within the remit of the Bank Recovery and Resolution Directive), insurers and reinsurers (but not insurance brokers)
  • Building Societies
  • Public-sector bodies
  • Further-education establishments, if they are grant-funded
  • State-funded primary and secondary schools

All lending decisions remain fully delegated to the accredited lenders.

Who decides on carrying-over holiday entitlement?

The Regulations do not require any prior agreement between an employer and employee that it was not reasonably practicable for holiday to be taken for it to be carried over.

However, if an employee requests holiday then an employer must have ‘good reason’ for refusing it due to coronavirus. The term ‘good reason’ is not defined so the Government will expect employers, employees and (if necessary on any dispute) the Courts to apply common sense.

The Regulations are not confined to key workers so could, in principle, be used by employers for a wider range of employees.

The Government guidance suggests that the following factors should be taken into account when considering whether it was reasonably practicable to take the leave in the relevant year:

  • Whether the business has faced a significant increase in demand due to COVID-19 that would reasonably require the worker to continue to be at work and cannot be met through alternative practical measures.
  • The extent to which the business’ workforce is disrupted by COVID-19 and the practical options available to the business to provide temporary cover of essential activities.
  • The health of the worker and how soon they need to take a period of rest and relaxation.
  • The length of time remaining in the worker’s leave year.
  • The extent to which the worker taking leave would impact on wider society’s response to, and recovery from, the effects of COVID-19.
  • The ability of the remainder of the available workforce to provide cover for the worker going on leave.
If you have to undertake collective consultation do you also have to carry out individual consultation?

Once the collective process concludes, an employer can make the decision to proceed with the restructure. They will then have 1-on-1 meetings with employees about the impact of the restructure on them. This will include consideration of alternative employment. There is no need to consult further about the proposal, merely the effect of the restructure on the individual.

What allowances has the Government proposed for company meetings?

The Government’s Corporate Insolvency and Governance Act introduces amendments to the current rules for companies on holding meetings, to address the difficulties companies are facing due to the Covid-19 pandemic.

The new provisions apply to meetings held between 26 March 2020 and 30 September 2020 (referred to as the “Relevant Period”). Subsequent regulations by the Government can be used to shorten this period or extend by up to 3 months but not past 5 April 2021.

The provisions will have retrospective effect, so meetings that were held after 26 March 2020 that may not have met the usual legal requirements due to lockdown, will be validated under these new provisions. These provisions under the Act make amends to relevant legislation and override a company’s articles of association.

For general meetings and certain other meetings of companies, the Act states that:

  • The meeting need not be held in any particular place;
  • The meeting may be held, and any votes may be cast, by electronic means or other means;
  • The meeting may be held without anyone being in the same place
  • Persons attending the meeting no longer have the following rights: the right to attend in person, the right to participate in the meeting other than by voting, or the right to vote by particular means.

The aim of these changes is to facilitate virtual meetings, and remove the need for a physical venue.

Where a company was required to hold its AGM between 26 March and 30 September 2020, it can be held at any time before 30 September 2020.  The Secretary of State has the power to make regulations to further extend the deadline.