Do I have to continue to pay furloughed staff while furloughed? Can I wait until I receive the money from the government?

To qualify for a grant under the scheme you must pay your furloughed staff the wages you are claiming for. Failure to do so may result in a HMRC investigation and/or claims from furloughed staff for unlawful deductions from wages and possibly constructive dismissal claims.

Normal benefits including non-monetary benefits should continue during furlough unless the individual has agreed in writing to reduce or remove a benefit during this time.

Employers are expected to apply for one or more of the financial support schemes available to be able to continue to pay staff.

Related FAQs

How should we deal with existing petitions already presented at court prior to 27 April?

You should speak to your advisors. We do not know presently how existing petitions will be dealt with by the Court. We do know that if any winding up order is made (based on a petition presented after 27 April), it could be found to be void and a creditor may face challenges. Even for petitions presented before 27th April, there is a risk that the Court will not be keen to make a winding up order so it is important that you look at the facts of your debt and weigh up all of the factors before deciding how to proceed.

What agreements will the CMA choose not to take enforcement action in respect of?

CMA guidance suggests that it will not take enforcement action in respect of agreements which:

  • Are appropriate and necessary to avoid a shortage, or ensure security, of supply
  • Are clearly in the public interest
  • Contribute to the benefit or wellbeing of consumers
  • Deal with critical issues that arise as a result of the Covid-19 pandemic
  • Last no longer than is necessary to deal with these critical issues
What are the current planning restrictions on supermarkets, food retailers and distribution centres concerning deliveries?

On 13 March 2020 the Secretary of State for Housing, Communities and Local Government issued a Written Statement in respect of delivery restrictions.

In this respect, many supermarkets, food retailers and distribution centres in England operate under planning restrictions (conditions and/or obligations) which limit the time and number of deliveries from lorries and other delivery vehicles which can take place particularly at night primarily to protect the residential amenity of nearby residential property.

Key points in the Statement include;

  • Given the exceptional challenges facing the UK from the coronavirus, it is vital that deliveries of food, sanitary and other essential products over the coming weeks can be made as quickly and safely as possible, minimising disruption to the supply chains. The likely pressures on driver capacity mean additional flexibility is needed so that retailers can accept deliveries throughout the day and night where necessary.
  • That planning enforcement is discretionary and that local planning authorities should act proportionately in responding to suspected breaches of planning control.
  • That local planning authorities should not seek to undertake planning enforcement action which would result in unnecessarily restricting deliveries of food and other essential deliveries during this period having regard to their legal obligations.

The Statement acknowledges that the increased frequency of deliveries particularly at night could have a temporary impact on residents. It therefore concludes that the Government will review the need for the flexibility outlined in the Statement after the pressure from the coronavirus has reduced and that it is the intention to withdraw it once the immediate urgency has subsided.

A link to the Written Statement is below.

https://www.parliament.uk/business/publications/written-questions-answers-statements/written-statement/Commons/2020-03-13/HCWS159/

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs