Skip to content

What happens to my mortgage after a divorce?

Within divorce proceedings, the court can order that a property is sold and that the mortgage is discharged from the proceeds of sale before the remaining balance is distributed to the parties, thus bringing the mortgage to an end.

The court also has the power to order that a property owned in joint names is transferred into one of the spouse’s sole name. However the court cannot order the mortgage provider to transfer the mortgage into one of the parties’ names. A number of options are available to resolve this. Depending on the financial circumstances, the spouse receiving the property may be able to re-mortgage the property into their sole name. If that is not possible and the mortgage has to remain in joint names, the court may require the spouse retaining the property to be responsible for the mortgage and provide an indemnity to the other party so that if they stop paying the mortgage, the other spouse can take action against them. Alternatively, in certain cases, a court may transfer the property into one spouse’s name but order that the other spouse continues to pay the mortgage, perhaps for a period of time such as until children reach a particular age.

Related FAQs

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What is the over-riding statutory duty for employers to ensure the health and safety of employees?

It is worth pointing out that, despite all the guidance, survey results and other advice about managing Covid-19 H&S risk in the workplace, the law has not been changed. None of the guidance is codified by regulation/legislation, which means that you are managing this risk in the context of existing H&S law.

In very simple terms, HASWA74 requires employers to take “all reasonably practicable steps” to ensure the health and safety of its employees (and anyone else affected by your business).

“Reasonably practicable” means to balance risk reduction against the time, money and effort required. If measures are grossly disproportionate, you wouldn’t be expected to take them, but there is a strong presumption in favour of taking any steps which will protect workers.

As part of managing the health and safety of your people, you must control the risks in your workplaces. To do this, look for what might cause harm to people while they work and decide whether you are taking reasonable steps to prevent that harm. This related duty under MHSWR is to ensure you undertake a “suitable and sufficient assessment of risks.”

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

What type of matters are the Courts still dealing with?

Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:

Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).

Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.

The full guidance can be found at:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/881019/Civil_court_listing_priorities_24_April_2020.pdf