What happens if I need to sign a new commercial lease in the future?
The outbreak is certainly going to have an impact on new lease negotiations.
Undoubtedly many transactions will be put on hold or indeed stop entirely. Where matters are ongoing, tenants may well look to strengthen rent suspension provision.
It is also possible that tenants and their representatives will also now seek to include termination rights for unseen events. In this regard, the concept of force majeure may start to appear more often in leases.
In both of the examples above, such attempts are not likely to be well received from landlords who will undoubtedly suggest that tenants ensure that their business interruption insurance policies are robust enough to protect the tenant in the event of any future pandemic events.
Another approach tenants might adopt going forwards in negotiations for a new lease (or indeed seeking to vary existing leases), is to move away from the traditional market rent model to a turnover rent arrangement. This will offer some protection going forward if trading conditions deteriorate, but again getting institutional landlords to agree such an approach may prove difficult.
Related FAQs
A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.
Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Funding audits are being paused and no new audits will be commenced during the lockdown period.
Employers who have apprentices on fixed-term contracts due to end during the pandemic should discuss arrangements with the apprentices including whether an extension to the contract can be offered to allow them to complete their apprenticeship.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here