Skip to content

What happens if a patient is admitted to hospital during the pandemic?

Related FAQs

Can landlords re-possess properties if tenants can’t afford to pay the rent because of the coronavirus outbreak?

After 25 March 2020, and until 30 September 2020, a landlord can only start possession proceedings against a tenant if they have served 3 months’ notice upon the tenant – irrespective of any grounds relied upon.

On 27 March 2020, the Court introduced new rules to put all possession proceedings (except against trespassers) on hold until 25 June 2020 – it means that the Court cannot make an order for possession or any other order that would cause someone to be evicted during that time.

These rules do not just apply to tenants who have fallen into rent arrears.

On 5 June 2020, the Government announced that this stay would be extended further until 23 August 2020.

This means that you can issue new possession proceedings (provided you have complied with the new temporary rules in relation to notice periods, if the notice was served since 25 March 2020) and you can continue with existing possession proceedings.

However, any progress you may be able to make in dealing with those proceedings is likely to be very limited – the Court will allow you to comply with directions orders that have already been made but non-compliance will not be punished (at least for the time being).

These rules, and the latest announcements, are in keeping with the Government’s expectation that landlords show compassion towards affected tenants and that all parties will work together to establish a suitable repayment plan to allow tenants to repay the arrears at an affordable rate.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
Are all employees required to stay at home?

No, where employees cannot work from home, and it is safe for them to return to work, they should do so.

Are there any exceptions to the obligation to return deposits?

The CMA sees only limited circumstances in which a full refund would not be given. The CMA accepts that where public health measures prevent a business from providing a service or the consumer from receiving it, the business may be able to deduct a contribution to the costs it has already incurred in relation to the specific contract in question.

This view reflects a relatively complex area of law under which parties are released from obligations under a contract if performance of that contract becomes impossible or illegal. This is called “frustration” of the contract. Under a law passed during World War II, a party to a contract that is frustrated who has incurred expenses is permitted, if the court thinks fit, to retain an amount up to the value of those expenses out of any money they have been paid by the other party.

The CMA’s view, however, is that this will not happen often, and that deductions from deposits will be limited.