What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

Related FAQs

If an employee has had a coronavirus test, can we require them to disclose evidence of their test results?

Obtaining an employee’s Covid-19 test result will amount to processing personal data for the purposes of the General Data Protection Regulation 2016/679 (GDPR) and information about an employee’s health is a special category of data (sensitive personal data under the Data Processing Act 2018 (DPA)).

In accordance with the GDPR and DPA, there must be lawful grounds for processing such information. Most employers rely on employees’ consent to obtain medical information and process sensitive personal data and if the employee is unwilling to give consent, you will not normally be entitled to the information.

Special category data can be processed lawfully if it is necessary for the performance of a task carried out in the public interest or in the exercise of official authority vested in the data controller. Employers may be able to require an employee to disclose their Covid-19 test if there is a substantial public interest, such as ensuring that the employee self-isolate if they have a positive test. However, there is a risk that this measure could be considered disproportionate particularly if it is enforced on all employees as a blanket measure.

Can I use flexible furlough to utilise an employee's holiday entitlement?

Employees are generally permitted to take holidays during furlough. However, Government guidance has been updated to state that “Employees should not be placed on furlough for a period simply because they are on holiday for that period.” If a period of furlough happens to coincide with an employee’s holiday then you should ensure that there are business grounds to support furlough being used in that instance so that it isn’t just being used as a means to fund holiday utilisation.

In a situation where a building has a B1 EWS1 rating but the insurance companies are either refusing to quote or saying the cladding is a fire risk (due to the result of the intrusive survey for the EWS1 rating) and quadrupling insurance premium, is there anything that will help with this situation in the Building Safety Act or the secondary regulations when they come in or do you think it is something case law will have to address?

The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements