Skip to content

What challenges to planning permission does the current lockdown situation present?

  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

Related FAQs

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What support is provided by the government under CBILS?

The Government will provide the lender with a partial guarantee (80%) against the outstanding facility balance, subject to an overall cap per lender. Note, the Government guarantee is to the lender only, the borrower will always remain 100% liable for the debt.

We understand that will make an initial claim for recovery against the borrower and will, once its normal recovery procedures have been completed, claim against the Government guarantee.

Can I force ways of reducing employment costs onto the workforce?

Some of these can be implemented by you, some need agreement or consultation and some depend on the wording of contracts. We’ll explain more in relation to each option.

What can I do if someone refuses to wear PPE for cultural and/or religious observance reasons?

Again, the primary point must be that an open dialogue is held with that individual to understand their concerns and to properly consider the impact that not wearing PPE will have on their abilities to undertake their duties. Consideration must be given as to whether there are any parts of their duties that they can undertake and whether they can remain in their role. Engage with the individual to ensure that you understand their point of view. What other duties can they do if they cannot do fulfil all the duties of their role?

How does this protect businesses entering into an insolvency process?

The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.

Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance,  in the event that the customer enters an insolvency procedure.

This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.

Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.

Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.