Skip to content

What are the new rules around holiday entitlement?

Workers who have not taken 20 days holiday entitlement due to Covid-19 can now carry it over into the next 2 leave years. It only applies where it was not reasonably practicable for a worker to take their annual leave due to the coronavirus.

Related FAQs

Can I still progress with stopping up applications?

We are working with many of our clients to progress with stopping up applications in order to divert/stop up highways and public rights of way affecting development sites. Due to lockdown restrictions the Department for Transport stalled the progress of applications because they were unable to comply with the statutory publicity requirements. We have very recently been contacted by the Department for Transport casework team who have confirmed that the stopping up/diversion applications can now be progressed. We are aware that Councils across the country are also now progressing with applications. Please contact us if you require any advice/assistance in respect of your application.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

What should I do if I have a hearing scheduled in the COP?

Parties are encouraged to review upcoming matters to assess the viability for there to be any agreement which can be reached in relation to the issues in dispute or to consider whether the case needs to proceed to a remote hearing. If directions or issues can be agreed between the parties, reducing the need for remote hearings, then that is the preferred option.

Can I reduce the risk of IR35 applying?

It is possible to review working arrangements for contractors before the new rules come into effect. This will require immediate action.

You could consider terminating current contracts and entering into new terms that reflect working arrangements for a self-employment arrangement.

Another possibility is encouraging contractors to abandon the PSC model and provide services under a compliant umbrella company.

In the event of a determination of employed status you should seek to enter new terms that at the very least reflect the new tax arrangements .