What are the early warning signs that a contractor may be in financial difficulty?
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
Related FAQs
If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.
If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Has there ever been a more important time for all staff to feel that they are able to raise concerns about their working environment?
It is a pertinent time to remind all staff that they should be able to raise concerns without the fear of repercussions. It is a good time to be reviewing and re-issuing your Freedom to Speak up/Whistleblowing policy to all. Likewise it is a good time to remind all staff that they should not treat others unfairly or detrimentally for raising health and safety concerns.
Both subjecting someone to a detriment because they have blown the whistle or raised health and safety concerns (and dismissing someone for the same) is unlawful.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Borrowers will not have to pay a guarantee fee. Lenders will pay a fee to access the scheme. The Government will make a Business Interruption Payment to cover the first 12 months of interest payments and any lender-levied fees, allowing smaller businesses to benefit from no upfront cost.
British Business Bank has indicated that following earlier discussions with the banking industry, some lenders indicated that they would not charge arrangement fees or early repayment charges to SMEs borrowing under the scheme. Each business should check the terms of the loans being made to ensure this is the case and what the interest rate and prepayment fees will be following the period in which the Government makes payment of these amounts.