Skip to content

What amount do you claim under the Flexible Furlough Scheme?

You will claim a pro rata’d amount of 80% of salary, based on the proportion of hours not worked out of the employee’s normal working hours (their “usual” hours).

There are 2 ways to calculate an employee’s usual hours, depending on whether they have fixed or variable hours/pay:

  • For those with fixed hours/pay, you take the number of hours worked in the pay period before 19 March 2020.
  • For those with variable hours/pay, you take the higher of:
  1. the average number of hours worked in the tax year 2019 to 2020 or
  2. the corresponding calendar period in the tax year 2019 to 2020.

If employees are paid per task or piece of work done, you should work out the usual hours for these employees in the same way as for other employees who work variable hours, if possible.

When you calculate the usual hours, you should include any hours of leave for which they were paid their full contracted rate (such as annual leave) and any hours worked as overtime (but only if the pay for those hours was not discretionary).

Related FAQs

Does the introduction of CLBILS assist private equity-backed businesses?

Under CBILS, for the purposes of calculating the applicant’s annual turnover, approved lenders have been aggregating turnover across the whole of the private equity investor’s portfolio meaning they failed to qualify for the scheme as they were deemed to exceed the £45 million threshold.

For private equity-backed businesses, the removal of the upper limit on annual turnover criteria for CLBILS seemingly avoids the issue of turnover aggregation across investment portfolios seen with the CBILS, potentially enabling more private equity sponsor portfolio companies to be able to access the CLBILS funding.

Who do the Procurement Policy Notes (PPN) apply to?

All three of the PPNs are effective immediately and apply to the following Contracting Authorities:

  • Central Government Departments
  • Executive agencies
  • Non-departmental public bodies
  • Local authorities
  • NHS bodies
  • The wider public sector

In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What is the guidance in relation to the Mental Capacity Act 2005 and Deprivation of Liberty Safeguards during the Covid-19 pandemic?

The Department of Health & Social Care has published guidance for hospitals, care homes and supervisory bodies on the Mental Capacity Act 2005 (MCA) and Deprivation of Liberty Safeguards (DoLS) during the coronavirus pandemic.

In many scenarios created or affected by the pandemic, decision makers in hospitals and care homes will need to decide:

  • if new arrangements constitute a ‘deprivation of liberty’ (most will not), and
  • if the new measures do amount to a deprivation of liberty, whether a new DoLS authorisation will be required (in most cases it will not be).

If a new authorisation is required, decision makers should follow their usual DoLS processes, including those for urgent authorisations.

A summary of the key points to be taken from the guidance is outlined below:

Use of the MCA and DoLS due to Covid-19

  • During the pandemic, the principles of the MCA and the safeguards provided by DoLS still apply.
  • It may be necessary to change the usual care and treatment arrangements, for example to provide treatment for people with Covid-19, to move them to a new hospital or care home to better utilise resources or to protect them from becoming infected.
  • All decision makers are responsible for implementing the emergency Government health advice  and any decision made under the MCA must be made in relation to a particular individual, it cannot be made in relation to groups of people.

Best interest decisions

  • In many cases, a best interests decision will be sufficient to provide the necessary care and treatment for a person who lacks the capacity to consent to the care and/or treatment arrangements during this emergency period.
  • If an individual has made a valid and applicable advance decision to refuse the treatment in question, then the relevant treatment, even for Covid-19, cannot be provided.

Delivering life-saving treatment

  • Where life-saving treatment is being provided in care homes or hospitals, including for the treatment of Covid-19, then the person will not be deprived of liberty as long as the treatment is the same as would normally be given to any person without a mental disorder.
  • The DoLS will therefore not apply to the vast majority of patients who need life-saving treatment who lack the mental capacity to consent to that treatment, including treatment to prevent the deterioration of a person with Covid-19.

The full guidance can be found here.

If there is an outbreak of coronavirus in a workplace – will it be RIDDOR reportable?

The reporting requirements relating to cases of, or deaths from, COVID-19 under RIDDOR apply only to occupational exposure, that is, as a result of a person’s work.

You should only make a report under RIDDOR when one of the following circumstances applies:

  • an accident or incident at work has, or could have, led to the release or escape of coronavirus (SARS-CoV-2). This must be reported as a dangerous occurrence
  • a person at work (a worker) has been diagnosed as having COVID-19 attributed to an occupational exposure to coronavirus. This must be reported as a case of disease
  • a worker dies as a result of occupational exposure to coronavirus. This must be reported as a work-related death due to exposure to a biological agent