Should you rely upon Statutory Demands issued after 1 March to present a Winding Up petition?
No. No action need be taken in relation to the demand but we would advise against presentation of a petition based upon any Statutory Demand issued between 1 March 2020 and the end of the restrictions. As you may be aware, with Winding Up there is no requirement to issue a Statutory Demand notice before proceeding so this is unlikely to create too many issues – click here to see whether you should issue petitions on other grounds.
There is nothing to prevent statutory demands being served at this time. However, there may be limited benefit as it cannot form the basis of a future winding up petition.
Related FAQs
Yes but the sponsor must report this on the Sponsor Management System within 10 working days and must follow normal employment law principles.
If this results in the sponsored worker’s falling below the minimum required salary the usual position is that they cannot continued to be sponsored. However the government has implemented a concession for sponsors who have ceased trading or temporarily reduced trading which allows the salary to be reduced to 80% of the figure stated on the Certificate of Sponsorship or £2,500 per month, whichever is lower.
There are four criteria which must be satisfied if an agreement is to be considered exempt:
- It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
- It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
- It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
- It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).
Details of your MHFAs should be posted somewhere that everyone can access easily – a specific area on an intranet or whatever alternative exists. Regular comms involving the MHFAs, webinar sessions, Q&A sessions and mental wellbeing drop in sessions are all ideas that may work well.
If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:
- Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
- A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all
If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.
Even if the right to terminate the contract does exist, there might be particular rules about the following:
- How much notice has to be given
- How such notice has to be served (for example, it might have to be in writing to a particular address)
- When the notice can be served (perhaps on an anniversary of the start of the contract)
- How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)
All of these factors must be taken into account, and any contractual processes for termination are followed.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.