Skip to content

Retraining and redeploying

If the business has areas requiring an increased workforce whilst others require a reduced workforce, staff can be retrained and redeployed across the organisation or even across a wider group of companies. This will not reduce the wage bill but will avoid the need for redundancies. Making fundamental changes to an employee’s role and duties will require their agreement following a fair selection and consultation process.

Related FAQs

Is it possible to proceed with a hearing in person for any COP matters?

Any hearings attended in person will need to be approved by the judge hearing the matter, if necessary, in consultation with the regional lead COP judge. Such requests are highly unlikely to be granted during COVID-19 unless there is a genuine urgency. However, it is deemed to be appropriate matters are likely to be adjourned on the basis that a remote hearing is not possible and a hearing in person is not safe or possible.

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

What guidance has the CMA issued about how it expects businesses to behave in response to the global pandemic?

On 30th April 2020, the CMA issued a guidance note setting out its views about how the law operates in relation to refunds.

Where a contract is not performed as agreed, the CMA considers that in most cases, consumer protection law will generally allow consumers to obtain a refund.

This includes the following situations:

  • Where a business has cancelled a contract without providing any of the promised goods or services
  • Where no service is provided by a business, for example because this is prevented by Government public health measures
  • A consumer cancels, or is prevented from receiving any services, because Government public health measures mean they are not allowed to use the services.

In the CMA’s view, this will usually apply even where the consumer has paid what the business says is a non-refundable deposit or advance payment.

This positon reflects the CMA’s previous guidance which they had issued in relation to the requirement of fairness in consumer contracts under the Consumer Rights Act 2015, which was that a clause in a contract that gives a blanket entitlement to a trader to cancel a contract and retain deposits paid is likely to be unfair, and therefore unenforceable – it would be unfair to a consumer to lose their deposit if the contract is terminated without any fault on their part, and if they had received no benefit for the payments made.

The CMA’s latest guidance therefore confirms their view that the Covid-19 outbreak does not change the basic rights of the consumer, and that they should not have to pay for goods or services that they do not receive.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Due to the lockdown and government guidelines, my partner and I have moved in to the house I own. Is there anything I need to be worried about?

Where a couple is not married, they have limited rights in relation to each other’s assets and these mainly relate to rights over property assets. There is complex Trust law which governs whether or not your partner could claim an interest in your property and it generally relates to where someone has invested in renovations on the property or promises have been made. If this is something you are concerned about, you and your partner could enter in to a Cohabitation Agreement. These Agreements can set out various matters, including who will pay the bills and where each of you would live if you separated. Most importantly, they can record your intentions about who owns the property and exclude any rights your partner would have against your property.