PODCAST: What are the legal implications I need to think about if I cancel an event?
Head of Commercial, Colin Hewitt, speaks with the team at NewcastleGateshead Initiative about the complexities of event cancellations and the associated legal implications.
Click here to listen to the full podcast.
Related FAQs
Safeguarding issues are relatively uncommon, however, if they do occur, the normal safeguarding procedure of the organisation should be followed.
The Commission has provided guidance as to measures which Member States can introduce without notification. These include:
- Measures which apply to all businesses within a Member State (for example the furloughing measures introduced by the UK Government)
- Measures providing support direct to consumers
- Measures which are already exempt from the notification requirement (discussed further below).
To respond to the crisis the European Commission has also issued a temporary framework to provide a basis for emergency aid to be notified for approval. The framework is initially in place until 31 December 2020. The Commission continues to keep this under review and has twice widened its scope to allow more types of aid to be notified. The type of measures covered include:
- The provision of guarantees (including guarantees for 100% of loans)
- The provision of loans at low interest rates, at zero interest rates or subordinated to senior debt
- Measures to support liquidity needs or to alleviate difficulties caused by the current crisis
- Measures to recapitalise businesses
- Measures to assist sectors hit particularly hard by the current crisis (eg transport)
- Measures targeted at COVID-19 such as research and development or production of products related to tackling the virus
The Commission has approved a UK Government “umbrella” notification to allow UK public authorities to adopt the measures permitted by the Commission framework. Therefore public authorities in the UK can use the Framework without notifying individual measures or schemes to the Commission.
The application is made via the Companies House website, and only takes a few minutes to complete. Companies House have indicated that the extension is “automatic and immediate” and will be for three months.
Having said that the extension is “automatic”, their website also says that Companies that have already extended their filing deadline, or shortened their accounting reference period, may not be eligible for an extension.
If an extension is granted, it will not affect the due date for filing accounts in future years – so the deadline will revert to the usual date for the next accounting period.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:
- Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
- A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all
If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.
Even if the right to terminate the contract does exist, there might be particular rules about the following:
- How much notice has to be given
- How such notice has to be served (for example, it might have to be in writing to a particular address)
- When the notice can be served (perhaps on an anniversary of the start of the contract)
- How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)
All of these factors must be taken into account, and any contractual processes for termination are followed.