PODCAST: What are the legal implications I need to think about if I cancel an event?
Head of Commercial, Colin Hewitt, speaks with the team at NewcastleGateshead Initiative about the complexities of event cancellations and the associated legal implications.
Click here to listen to the full podcast.
Related FAQs
Yes but the sponsor must report this on the Sponsor Management System within 10 working days and must follow normal employment law principles.
If this results in the sponsored worker’s falling below the minimum required salary the usual position is that they cannot continued to be sponsored. However the government has implemented a concession for sponsors who have ceased trading or temporarily reduced trading which allows the salary to be reduced to 80% of the figure stated on the Certificate of Sponsorship or £2,500 per month, whichever is lower.
It is possible to review working arrangements for contractors before the new rules come into effect. This will require immediate action.
You could consider terminating current contracts and entering into new terms that reflect working arrangements for a self-employment arrangement.
Another possibility is encouraging contractors to abandon the PSC model and provide services under a compliant umbrella company.
In the event of a determination of employed status you should seek to enter new terms that at the very least reflect the new tax arrangements .
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
The current position is that the PSC is responsible for assessing whether IR35 applies. This current regime has been difficult to police by HMRC and HMRC considers there is widespread flouting of the rules by contractors.
From April 2021 the responsibility for assessing whether IR35 applies will shift to the end user/client (with the exception of ‘small’ companies) which will require an assessment to be carried out on a contract by contract basis. HMRC anticipates that this will be easier to monitor and that end user businesses will be more compliant.
The reformed regime will apply to payments made on or after 6 April 2021 for services carried out on or after this date.