Skip to content

ONLINE EVENT: How to avoid risks in customer agreements and supply chains during Covid-19

Hosted by Advanced Manufacturing Forum, Partner, Matt Cormack discussed in this webinar how to avoid risks associated with your customer and supply chain contracts during this challenging Covid-19 period.

The webinar covers common questions such as:

  • Can force majeure excuse me or my suppliers from paying on time?
  • What are the risks to my business if I can’t perform on time due to Covid-19?
  • What will happen to my contracts if the Government takes steps to require me to close down my facility?

To watch the full recording, please click here. (To note the recording begins at 10 minutes)

If you have any follow up questions, please do not hesitate to contact one of our lawyers detailed below or use our ‘ask us a question‘ feature.

Related FAQs

Which charities will benefit from this funding and when – Key Services?

The Government will allocate £360 million to charities providing key services and supporting vulnerable people during the crisis.  £200 million of this amount will be paid to Hospices UK to be distributed to hospices to help increase capacity and give stability to the sector.  The remaining amount is to be allocated to:

  • St Johns Ambulance to support the NHS
  • victims charities, including domestic abuse, to help with potential increase in demand for charities providing these services
  • charities supporting vulnerable children, so they can continue delivering services on behalf of local authorities;
  • disabled people
  • Citizens Advice Bureau to increase the number of staff providing advice during this difficult time

The Government Departments will identify priority recipients, with the aim that these charities will receive money in the form of a cash grant over the next few weeks and by the end of April to assist in paying amongst other costs April’s wage bill.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

How might the transition to a "new normal" impact on contracts?

The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.

This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.

For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?

Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.

Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.

Is it legally enforceable?

The guidance is non-statutory and is not binding on business. However, businesses should be aware that there might be reputational consequences if they do not follow the guidance; we have already seen in the context of taking advantage of furlough funding that not being in breach of the law is no protection against negative publicity. Further to the extent a contract expressly requires parties to act reasonably, it could be expected that this guidance is one of the factors a court would consider in determining what is reasonable.