Skip to content

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Related FAQs

I am agreeing a financial settlement with my ex-spouse. Should we carry on negotiating despite COVID-19?

No. Before continuing any negotiations, you need to strongly consider whether now is the best time to settle. There is a myriad of uncertainty due to the pandemic, with unemployment rates increasing, volatility in the stock markets and difficulties regarding placing valuations on assets. This could all lead to the financial settlement being unfair to you and cause you financial difficulties in the future.

Any financial settlements reached following marital separation should be embodied in to a Court Order, to prevent future claims from your ex-spouse. As a general principle, although maintenance orders are always variable, financial orders in respect of capital (e.g. house, cash, investments, pensions) are final and it is very difficult to set aside a Court Order. The question will be whether or not the pandemic is judged as a Barder event, which broadly means something viewed as unforeseen. It would be challenging for you to argue that the effects of COVID-19 are unforeseen given the widespread expectation of an economic crisis. The Court previously found against a husband who wanted to revisit an Order that he said was unaffordable following the 2008 financial crisis, with one Judge commenting that a 90% drop in the Husband’s share price was a “natural process of price fluctuation”.

Even if you informally agree a settlement with your ex-spouse, and you do not have this reflected in a Court Order, your ex-spouse may still rely on this agreement within future Court proceedings and argue that you should be held to it.

It is, therefore, very dangerous to be reaching any financial settlements at this time with your ex-spouse without careful consideration and legal advice. Further, even if an agreement is reached, market volatility can mean longer implementation times, especially when a settlement relies on the sale of property.

How much will I get under the scheme?

If you are eligible you will get a taxable grant of 80% of the average profits from the following tax years (where applicable):

2016-2017

2017-2018

2018-2019

HMRC will add the total profit in each of the three tax years (if applicable). This will then determine the monthly payment, subject to the cap of £2500.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

What if a contractor is deemed to be employed?

The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.

If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.

Should my apprentice continue their training during the coronavirus outbreak, even if they’re furloughed?

The Government maintains that apprenticeships will be an important part in the economic recovery post-lockdown and therefore ESFA is encouraging training under apprenticeships to continue, even where an apprentice is furloughed, provided that the training does not provide services to or generate income for their employer. E-learning is being encouraged as a method of delivery.