Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Related FAQs
Aside from the CBILS Scheme, the Government have, or are in the process of, implementing several different schemes to support businesses financially through the Covid-19 outbreak.
On 13 March 2020 the Secretary of State for Housing, Communities and Local Government issued a Written Statement in respect of delivery restrictions.
In this respect, many supermarkets, food retailers and distribution centres in England operate under planning restrictions (conditions and/or obligations) which limit the time and number of deliveries from lorries and other delivery vehicles which can take place particularly at night primarily to protect the residential amenity of nearby residential property.
Key points in the Statement include;
- Given the exceptional challenges facing the UK from the coronavirus, it is vital that deliveries of food, sanitary and other essential products over the coming weeks can be made as quickly and safely as possible, minimising disruption to the supply chains. The likely pressures on driver capacity mean additional flexibility is needed so that retailers can accept deliveries throughout the day and night where necessary.
- That planning enforcement is discretionary and that local planning authorities should act proportionately in responding to suspected breaches of planning control.
- That local planning authorities should not seek to undertake planning enforcement action which would result in unnecessarily restricting deliveries of food and other essential deliveries during this period having regard to their legal obligations.
The Statement acknowledges that the increased frequency of deliveries particularly at night could have a temporary impact on residents. It therefore concludes that the Government will review the need for the flexibility outlined in the Statement after the pressure from the coronavirus has reduced and that it is the intention to withdraw it once the immediate urgency has subsided.
A link to the Written Statement is below.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
No. The Home Office has confirmed that sponsors do not need to report sponsored workers as working from home, where this is directly related to the coronavirus outbreak.
However any UK employers who sponsor overseas workers, should also ensure that they remain compliant with their other sponsor licence duties, which includes reporting any change to an employee’s salary and duties.
The MHFA training makes this clear, it should be made clear in the MHFA role specification and procedures and discussed during regular MHFA peer support and MHFA surgery sessions. It is important to ensure that where an Employee Assistance Programme is in place, all MHFAs have details of that scheme available so they are able to instantly share details of the scheme with those who require support. If in doubt due to serious concerns then using 999 or Samaritans is an option.