Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Related FAQs
Yes but the sponsor must report this on the Sponsor Management System within 10 working days and must follow normal employment law principles.
If this results in the sponsored worker’s falling below the minimum required salary the usual position is that they cannot continued to be sponsored. However the government has implemented a concession for sponsors who have ceased trading or temporarily reduced trading which allows the salary to be reduced to 80% of the figure stated on the Certificate of Sponsorship or £2,500 per month, whichever is lower.
There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.
Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.
A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.
ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”
The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.
PPN 01/20: Responding to COVID-19
The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.
This PPN provides guidance for the following circumstances:
- Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
- Direct award due to an absence of competition or protection of exclusive rights
- Call off from an existing framework agreement or dynamic purchasing system
- Call for competition using a standard procedure with accelerated timescales
- Extending or modifying a contract during its term
PPN 02/20: Supplier relief due to COVID-19
PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.
This PPN provides guidance for the following circumstances:
- Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
- Put in place appropriate payment measure to support supplier cash flow
- Where contract payments are based on ‘payment by results’ make payments based on previous invoices
- Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
- Ensure invoices submitted by suppliers are paid immediately on receipt
PPN 03/20: Use of Procurement Cards
The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.
This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:
- Increase a single transaction limit to £20,000 for key card holders
- Raise monthly limits on spending with procurement cards to £100,000 for key card holders
- Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs
Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.
The PPN also advises that by 30 April 2020, in scope organisations should:
- Ensure that a number of appropriate staff have the authority to use these cards
- Open all relevant categories of spend to enable these cards to be used more widely
The Commission has provided guidance as to measures which Member States can introduce without notification. These include:
- Measures which apply to all businesses within a Member State (for example the furloughing measures introduced by the UK Government)
- Measures providing support direct to consumers
- Measures which are already exempt from the notification requirement (discussed further below).
To respond to the crisis the European Commission has also issued a temporary framework to provide a basis for emergency aid to be notified for approval. The framework is initially in place until 31 December 2020. The Commission continues to keep this under review and has twice widened its scope to allow more types of aid to be notified. The type of measures covered include:
- The provision of guarantees (including guarantees for 100% of loans)
- The provision of loans at low interest rates, at zero interest rates or subordinated to senior debt
- Measures to support liquidity needs or to alleviate difficulties caused by the current crisis
- Measures to recapitalise businesses
- Measures to assist sectors hit particularly hard by the current crisis (eg transport)
- Measures targeted at COVID-19 such as research and development or production of products related to tackling the virus
The Commission has approved a UK Government “umbrella” notification to allow UK public authorities to adopt the measures permitted by the Commission framework. Therefore public authorities in the UK can use the Framework without notifying individual measures or schemes to the Commission.
Homeworking can cause work-related stress and affect people’s mental health and being away from managers and colleagues could make it difficult to get proper supervision and support.
Encourage your employees to keep in touch. Put procedures in place so you can keep in direct contact with home workers and can recognise signs of stress as early as possible. Use group chat and video chat tools imaginatively.
Have an emergency point of contact and share this so people know how to get help if they need it.
People are much more anxious than usual and may be less productive as a result – recognise this and try to be patient.