Skip to content

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Related FAQs

I hold a licence but can’t trade. Can I terminate it?

A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.

Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
What are the changes to the law?

On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process.  This has very important consequences for many businesses as it could expose them to greater financial risks.

Will there be further measures for self-employed announced?

The Government assured parity for the self-employed but it has since accepted that this would be difficult to achieve. The Association of Independent Professionals and the Self-Employed (IPSE) has worked closely with the Government on implementing the current self-employment income support scheme. IPSE has confirmed that it will continue to work on helping to extend measures to all freelancers in need as a result of Covid-19.

The Government announced an extension to the Self-Employment Income Support Scheme from 1 November 2020.

 

How is an establishment defined?

The definition of a relevant establishment is a question of fact for an Employment Tribunal. Guidance from case law says that ‘establishment’ should be interpreted very broadly (so as to avoid employers escaping the need to collectively consult), and may consist of:

  • A distinct entity
  • With a certain degree of permanence and stability
  • Which is assigned to perform one or more tasks
  • Which has a workforce, technical means and a certain organisational structure to allow it to do so

However, there is no need for it to have the following:

  • Legal, economic, financial, administrative or technological autonomy
  • A management which can independently effect collective redundancies
  • Geographical separation from the other units and facilities of the undertaking