Skip to content

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Related FAQs

Would you suggest using a different name for a MHFA, maybe a MH champion, to encompass the wider pro-active role?

This may be a good idea – whatever name they are given, it is essential that MHFAs are empowered to take a proactive approach to organisational mental health and that they have the bandwidth to be able to discharge their responsibilities.  The name should reflect the culture of the organisation, the key aspect is awareness and accessibility – identifying a name for your company that supports this is key.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Flexible working

Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.

A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.

Will councillors still be able to vote if they can’t meet in person?

Local government legislation formerly stipulated that councillors must be physically present to vote and this requirement has already led to the widespread cancellation of Council meetings.  There is a limit to what can be achieved under the chair’s emergency powers and delegation to officers.

The Government has now legislated to allow for remote voting until 7 May 2021. The secondary legislation required was issued in draft on 2 April and has been in force since Saturday 4 April.

The legislation allows for committee meetings to go ahead where members and any members of the public attending remotely can all times “hear (and where possible see) and be heard (and where possible be seen) by the other members in attendance”.

It remains to be seen how many local authorities take up the opportunity to hold a virtual committee meeting. Concern has been expressed that the demographic of local councillors may mean that members have difficulty with the technological mechanisms for holding such meetings. However, the message from the Secretary of State is clear that wherever possible, the planning system should keep moving in these current times.

Which properties should I prioritise?

Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.

Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.