I’m a housing provider. How do I continue to manage disrepair during the coronavirus outbreak?
The practicalities and processes regarding disrepair claims will undoubtedly be affected. Housing providers will have to adopt a risk-based approach and consider government guidance to handle claims going forward. Key points to consider are:
- Compliance with the Pre-Action Protocol for Housing Conditions Claims (particularly disclosure)
- The practicalities of inspection
- Non-urgent repairs
Related FAQs
All employers have a duty to prevent illegal working, and carrying out proper Right to Work checks are a fundamental part of this. In light of Covid-19, the Home Office has brought in some temporary measures for employers to use to carry out the requisite Right to Work checks. Failure to follow these could lead to enforcement action and penalties.
The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.
PPN 01/20: Responding to COVID-19
The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.
This PPN provides guidance for the following circumstances:
- Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
- Direct award due to an absence of competition or protection of exclusive rights
- Call off from an existing framework agreement or dynamic purchasing system
- Call for competition using a standard procedure with accelerated timescales
- Extending or modifying a contract during its term
PPN 02/20: Supplier relief due to COVID-19
PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.
This PPN provides guidance for the following circumstances:
- Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
- Put in place appropriate payment measure to support supplier cash flow
- Where contract payments are based on ‘payment by results’ make payments based on previous invoices
- Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
- Ensure invoices submitted by suppliers are paid immediately on receipt
PPN 03/20: Use of Procurement Cards
The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.
This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:
- Increase a single transaction limit to £20,000 for key card holders
- Raise monthly limits on spending with procurement cards to £100,000 for key card holders
- Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs
Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.
The PPN also advises that by 30 April 2020, in scope organisations should:
- Ensure that a number of appropriate staff have the authority to use these cards
- Open all relevant categories of spend to enable these cards to be used more widely
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
The change in the law has the potential to place much greater financial risks on suppliers, making it more difficult to exit a contract with a customer of doubtful solvency. This will place increased emphasis on appropriate financial due diligence and credit checking before entering into supply contracts.
In addition to the obvious issues around financial risk, suppliers will also need to think carefully about how their contracts are drafted. For example, any form of right that is drafted so as to be triggered on customer insolvency will clearly be problematic. These could include:
- Retention of Title provisions, which are commonly drafted so that the right to enter premises and retake possession of the goods is triggered on insolvency;
- Provisions for brand protection, which seek to control how goods are dealt with on termination of the contract.
This is potentially a very significant development for many businesses. We would strongly recommend specialist advice be obtained so that:
- businesses understand the potential increased risks faced; and
- where possible, contracts are updated so that appropriate protections are maintained.
The coronavirus outbreak has seen State support being given to businesses on an unprecedented scale.
This issue is likely to be increasingly relevant as Governments seek to protect and stimulate their economies as they emerge from lockdown.
How have the rules been relaxed in the context of the crisis and what facets of the existing law can be used for the State to provide support to undertakings?