Skip to content

I am dealing with an estate where the bank has sent me an indemnity to obtain the funds. Will the bank accept my signature without it being witnessed by my solicitor?

If you have obtained a Grant of Probate or Grant of Letters of Administration there should be no need to complete an indemnity, merely an account closure form. If however you have not yet obtained a Grant but the bank is willing to release funds then they will generally require an indemnity to be executed. Several banks and building societies including Barclays, Lloyds, HSBC and Santander have signed up to the British Banking Association’s voluntary Bereavement Principles, one of which is to support the bereaved according to their personal needs and work with you to resolve everything as quickly as possible.

If the indemnity requires a solicitor to act as a witness, you should contact the bank to see what they are willing to do to get around the problem, given the current situation.

Related FAQs

Do I need Planning Permission to change the use of a warehouse or factory unit to a temporary mortuary?

Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.

Sui generis uses are not within any Use Class. Consequently planning permission is required for the:

  • Change in the use to a sui generis use
  • Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class

Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.

Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.

https://www.parliament.uk/business/publications/written-questions-answers-statements/written-statement/Commons/2020-03-13/HCWS159/

Depending on the form of the enforcement action, there could be a right of appeal.

Will COP hearings still be open to the public?

Transparency is considered to be central to the philosophy of the COP. The guidance provides details on issues concerning transparency of proceedings and involvement/attendance of P. Whilst there will be some difficulties with ensuring that remote hearings are accessible to the public as an ‘open court’, provisions have been made for the continued presence of the press where the facilities can accommodate this.

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
One of my employees has contracted Covid-19, should I report it under RIDDOR?

You must only make a report under RIDDOR (The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013) when:

  • An unintended incident at work has led to someone’s possible or actual exposure to coronavirus. This must be reported as a dangerous occurrence
  • A worker has been diagnosed as having COVID 19 and there is reasonable evidence that it was caused by exposure at work. This must be reported as a case of disease
  • A worker dies as a result of occupational exposure to coronavirus.