How the furlough scheme changed from 1 July – what is flexible furlough?
From 1 July 2020 the furlough scheme has been operating more flexibly.
The key changes from 1 July 2020 were:
- All furloughed employees are subject to the new flexible furlough rules and the new basis for calculating claims
- Furloughed employees can be brought back to work on a part-time basis for any amount of time and can work any work pattern
- Employers can claim for the hours not worked compared the hours the person would normally have worked in that period
- There must be a new written furlough agreement in place to record the agreement with the furloughed employee to return to work part-time
- The new agreement (including a collective agreement) must be made before any period of flexible furlough begins but it may be varied at a later stage if necessary. The agreement must be incorporated into the employee’s contract of employment, either expressly or impliedly
- Employers must keep a record of this agreement until at least 30 June 2025, and they must also keep a record of the hours the furlough employee worked and the hours that they were furloughed
- Employees can be furloughed from 1 July 2020 for any amount of time and more than once
- However, if you re-furloughed an employee after 10 June but before 1 July 2020, they had to be furloughed for an initial period of three consecutive weeks
- Claims for payments under the scheme must not cross calendar months so if you are claiming for the initial three week period of a re-furloughed employee who was furloughed on 12 June for example, you must submit separate claims for the dates in June and July
- Although flexible furlough agreements can last any length of time, you should only submit a claim to HMRC once a week.
Related FAQs
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
The Vice President of the COP, Mr Justice Hayden, has issued guidance to assist parties during this challenging time.
The latest guidance with all relevant updates on developments is available on the judiciary website here.
- A taxable grant worth 80% of the average monthly profit over the last three years (one or two years will be reviewed for those who do not have three years of tax returns)
- The grant will be capped at £2,500 per month
- The scheme was initially available for three months and has been extended as necessary
- Individuals claiming a grant can continue to do business (unlike employees who must not work when furloughed)
That will depend on the terms of your facility and the stance taken by your bank.
Banking facilities often place obligations on businesses to stick to certain financial criteria. For example, an obligation to keep turnover or profit above certain levels or a commitment to keep the bank’s exposure within an agreed percentage of the value of the company’s assets (known as loan to value ratio).
The consequences of breaching those covenants will depend on the terms of your facility, but normally this amounts to an event of default. Events of default can result in the loan (or whatever form the facility takes) becoming repayable and could give the bank certain powers to take action to recover the money that they are owed.
Whether the bank will take action during these unprecedented times is another matter, particularly given the extent of support being offered to businesses via mainstream lenders and the political desire to keep viable businesses up and running. Lenders themselves will no doubt wish to remain supportive where possible. The underlying performance of the business (and whether but for the effects of Covid-19 it would have been in a healthy financial position), the relationship you have with the bank and your history with them will no doubt be relevant to the approach taken by the bank. However, early engagement with your bank (as well as other key stakeholders in the business) will be important.