How might the transition to a “new normal” impact on contracts?
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.
Related FAQs
If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:
- Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
- A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all
If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.
Even if the right to terminate the contract does exist, there might be particular rules about the following:
- How much notice has to be given
- How such notice has to be served (for example, it might have to be in writing to a particular address)
- When the notice can be served (perhaps on an anniversary of the start of the contract)
- How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)
All of these factors must be taken into account, and any contractual processes for termination are followed.
The Government’s guidance says walk, cycle or drive to work and avoid public transport if you can. Businesses will need to support workers in adopting alternative travel methods to reduce exposure to the virus. You could consider staggering start and finish times for shifts to reduce commuting during peak hours, or support cycling with secure storage facilities and a drying room.
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
As discussed above, Covid-19 will inevitably deplete the workforce of housing providers in the foreseeable future. It would be prudent to consider making short-term policy changes to deal with this situation and manage the expectations of tenants going forward. A key policy change to consider is the extension of the standard lead-time for completing all non-urgent repairs and inform tenants of this change.
Such a change will also reduce pressure on landlords and front-facing staff.
As above, employers must protect the interests of their staff, particularly regarding health and safety. Extra care should be exercised when assessing the level of emergency of a repair on a case by case basis. All efforts should be made to reduce the number of attendances at properties by repair staff, whilst keeping all tenants safe.
As ever, communication is key – the pandemic cannot be used as a blanket excuse for abstaining from all duties and obligations. Housing providers must take a pragmatic approach in safeguarding customers whilst considering the interests of is workers. Maintaining lines of communication with all parties remains paramount.
The Competition and Markets Authority (CMA) has issued a number of guidance documents about the application of competition law rules during the coronavirus outbreak. In general, the competition law rules are being relaxed in very specific circumstances.