How might the transition to a “new normal” impact on contracts?
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.
Related FAQs
During these unusual times, we are all having to adapt to what has become the ‘new normal’ and implement changes in how we carry out civil cases. If you are to give evidence in a remote hearing, whether this is by Microsoft Teams, Skype for Business or the Cloud Video Platform, we have pulled together a quick and useful guide below on what would be expected by the courts:
Before the hearing
- Make sure that you have access to the video-conferencing software that will be needed for the hearing. We will tell our clients and their witnesses in advance which platform will be used. The courts have increasingly been using Skype for Business to conduct the hearings (but you may find other platforms being used)
- Test that your camera and microphone are working and it is clear to see/hear you.
- Dress appropriately, as if it was an in-person hearing, and use the same formalities.
- Ensure that the background which is visible on your screen is appropriate and allows for your face to be clearly seen. A ‘blur background’ option may also be available on your settings which you may prefer.
- Make sure that your mobile phone is on silent and you are in a location where there will be no/minimal distractions. You should be on your own in a room when giving evidence, however, as we have all experienced with working from home, sometimes interruptions such as children appearing cannot be avoided.
- Join the call ahead of the allocated time, in order to allow for any small technical difficulties.
During the hearing
- Have a copy of the hearing bundle to hand, so that you can follow the proceedings (this may be in hard copy or soft copy). You are not allowed any other notes or papers, whether hard copy or electronic, in front of you when giving evidence.
- Unless addressing the Judge or you have been directly asked a question, keep your microphone muted.
- When giving evidence, you must make sure both your camera and your microphone are switched on.
- Remote hearings can be difficult and if you do not understand or you do not hear a question properly, then do ask for the question to be repeated/re-framed.
- You should not move away from the screen without permission from the Judge. The Judge will allow time for breaks.
- Address the judiciary and other advocates the same way as you would if you were in a physical courtroom.
- It is permitted to drink water throughout the hearing, but mugs of tea and/or coffee are probably best avoided. It is also not permitted to eat food during the hearing.
- Don’t panic if someone walks into the room or the dog starts barking because there is a knock at the door. Judges are only too aware about what might happen. Communication is key and if the interruption has interfered with your train of thought or the evidence you are giving then do say so.
- Be aware that all evidence is recorded and that a transcript of all evidence can be obtained at a later date.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
A common feature of corporate acquisitions is that part of the consideration is paid on deferred terms or by way of earn out over a period of years following completion. Where deferred consideration is payable, this is either on the basis that outstanding payments will be made on scheduled dates or, less usually, subject to certain agreed (typically financial) objectives being met. These objectives almost always relate to a period before completion of the deal and are dealt with as part of a completion accounts mechanism.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Because they all have devolved governments, when there are changes to spending levels in England, the Government makes adjustments to the amount of public expenditure allotted to Scotland, Wales and Northern Ireland. In this case £60 million will be made available for all of the devolved administrations as a result of the £370 million funding allocated to charities in England. This is broken down as follows:
- £30 million for the Scottish Government
- £20 million for Welsh Government
- £10 million for the Northern Ireland Executive
There may be further allocations, dependent on the final projects funded, through the £360 million direct grant pot.