Skip to content

How long does a claim take?

There is no hard and fast rule as to how long a claim under the 1975 Act can take.  If a dispute is settled early into the process then resolution can be reached in a matter of weeks or months.  If, on the other hand, matters have to proceed all the way to trial then it is not unheard of for disputes under the 1975 Act to last anywhere between 12-18 months

Related FAQs

What should I do if I think this is relevant to my contracts?

It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:

  • Ensure that initial contact with your counterparty is framed in the correct way
  • Ensure that any variations are fully documented so that both parties are fully protected
My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Will I have to go to court?

The vast majority of disputes settle without ever reaching a final hearing with something in the region of 2-5% of all cases actually ending up in court at a final trial.  So whilst it is very unlikely you would need to attend a court hearing, it is always a possibility.

What should I do if my apprentice is due to finish their fixed-term contract during the pandemic?

Employers who have apprentices on fixed-term contracts due to end during the pandemic should discuss arrangements with the apprentices including whether an extension to the contract can be offered to allow them to complete their apprenticeship.

I’m in the process of litigation. What happens during the coronavirus outbreak?

The best advice is that parties should proceed as they would have done before the crisis began.