How long does a claim take?
There is no hard and fast rule as to how long a claim under the 1975 Act can take. If a dispute is settled early into the process then resolution can be reached in a matter of weeks or months. If, on the other hand, matters have to proceed all the way to trial then it is not unheard of for disputes under the 1975 Act to last anywhere between 12-18 months
Related FAQs
- On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
- A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
From 6 April 2022, the process will change. The first stage in the divorce process is to issue a divorce application with the court. This is the document which outlines that your marriage has broken down irretrievably. If you are a sole applicant, the divorce application will be sent to your husband/wife, and they will have to acknowledge receipt of the application in order for the divorce to proceed. Alternatively, you and your husband/wife can make a joint application together, and the divorce application will be sent to both of you for acknowledgment.
The law lays down a minimum allowable period of 20 weeks between the application and the conditional order. After 20 weeks you can apply to the court for a conditional order. This is the stage when the court satisfies themselves that you are entitled to a divorce. Once you receive your conditional order, you can apply for your final order after 6 weeks and one day. The Final Order formally ends your marriage.
There can be complications to the divorce process if, for example, your husband/wife refuses to acknowledge the divorce application. At these times it is in your best interests to obtain legal advice as to the best way to proceed.
Our experienced divorce lawyers understand the stress of facing a divorce and can make the process simple, hassle free and affordable. They have also prepared this article which provides further detail on the divorce process.
Interestingly, there is currently no ‘single’ technology to be used by the judiciary within the protocol. The court and parties must choose from a selection of possible IT platforms or audio/telephone hearing (further details available in the guidance e.g. Skype for Business, Microsoft Teams, Zoom etc.) The particular platform must be agreed at the outset of each case and then specified in the case management order. The guidance issued also sets out the basic principles which apply when conducting remote hearings.
Physical bundles may not be regarded as safe for public health and there are obvious difficulties in providing them with the current restrictions in place. Electronic bundles should be provided in PDF format, preferably paginated, indexed and bookmarked. The bundles should only contain documents and authorities that are essential to the issues required to be decided at the remote hearing and should be filed with the court by email.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.