How do I make arrangements for end point assessments for apprentices?
Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.
Related FAQs
Yes but the sponsor must report this on the Sponsor Management System within 10 working days and must follow normal employment law principles.
If this results in the sponsored worker’s falling below the minimum required salary the usual position is that they cannot continued to be sponsored. However the government has implemented a concession for sponsors who have ceased trading or temporarily reduced trading which allows the salary to be reduced to 80% of the figure stated on the Certificate of Sponsorship or £2,500 per month, whichever is lower.
As the pandemic progresses, more and more people will be forced to self-isolate and, inevitably, both tenants and staff will be affected. Put plans in place to mitigate the impact that this may have, particularly regarding staff shortages. The most important focus here should be communication.
The Covid-19 outbreak will affect the pace of everyday life and delays will be expected. Rather than allowing the pandemic to take over completely, it is important to maintain open communication with tenants as much as possible and inform them of any front-facing challenges that you may face.
The Protocol does envisage that delays may occur and allows for some degree of flexibility. Whilst all efforts should be made to conduct inspections where practical and possible, it should be expected by all parties that timescales will be extended during this crisis. It is fundamental, however, that all changes made to standard practice are communicated and explained to tenants to manage expectations.
Similar flexibility should be afforded to tenants. As households are required to isolate it will not always be possible to gain access to properties as would usually be expected and required. Likewise, vulnerable people will wish to protect themselves and their families and may refuse access on this basis. During this period, a degree of understanding must be exercised and concessions made.
Inspections may be delayed if anyone in the household has symptoms. A questionnaire should be prepared for those visiting properties to assess so far as possible the risk; Personal Protective Equipment should be issued to those visiting, and government guidelines followed.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Conduct risk assessments! Your RA must cover every foreseeable risk arising from a return to the workplace, including the impact of reduced staff levels and any operational/administrative changes necessary to ensure social distancing.
Appropriate steps should be taken to manage and mitigate identified risks. Where this is not possible, businesses need to decide whether certain activities are necessary for the business to operate or if they can be temporarily put on hold.
Keep a close eye on the comprehensive Government guidance: https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19
In particular focus on social distancing and workplace health measures. This guidance will evolve over time and you will need to be sure that your organisation is sticking to it AND reviewing and updating its risk assessment.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.