How do I make arrangements for end point assessments for apprentices?
Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.
Related FAQs
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
The Coronavirus pandemic will have impacted businesses in many different ways, but some of the most likely impacts that could have a legal implication are as follows:
- Services were not performed in accordance with contract during the period of disruption. This could be a reduction in volume of services performed, a suspension of services, or performance in a way that does not comply with contractual KPIs
- Late delivery or non-delivery of goods because of factory closures, or disruption in the supply chain
- Changes being agreed between parties to contracts to deal with the consequences of the Covid-19 outbreak
As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.
If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.
If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
If you do not have a justifiable reason for insisting that your employees have the vaccine (see FAQ above) your employee could resign and bring a claim of constructive unfair dismissal if they have more than 2 years’ continuous employment. This would be on the basis that you have breached trust and confidence.
If the vaccine includes pig gelatine (as many do), and the employee refuses on religious or because they are vegan, you may face a claim for discrimination under the Equality Act 2010.