Skip to content

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times

Related FAQs

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

I hold a licence but can’t trade. Can I terminate it?

A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.

Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.

Can the apprentice take a break or pause in learning due to coronavirus?

A break or pause in learning can be initiated where the interruption to learning due to Covid-19 is greater than four weeks. This must be reported as a formal break in learning. In such circumstance the funding to the training provider will be suspended for the duration of the break. Previously, the rules only allowed an apprentice to initiate this break in learning but this has been expanded to give employers and training providers the right to initiate this. Training providers should continue with their monthly IRL submissions to the ESFA. During breaks in apprenticeships it is not necessary for the apprentice to comply with the minimum of 20% on the job training requirement but this will resume when the break ends.

What will be the impact of the proposals on suppliers?

The change in the law has the potential to place much greater financial risks on suppliers, making it more difficult to exit a contract with a customer of doubtful solvency.  This will place increased emphasis on appropriate financial due diligence and credit checking before entering into supply contracts.

In addition to the obvious issues around financial risk, suppliers will also need to think carefully about how their contracts are drafted.  For example, any form of right that is drafted so as to be triggered on customer insolvency will clearly be problematic.  These could include:

  • Retention of Title provisions, which are commonly drafted so that the right to enter premises and retake possession of the goods is triggered on insolvency;
  • Provisions for brand protection, which seek to control how goods are dealt with on termination of the contract.

This is potentially a very significant development for many businesses.  We would strongly recommend specialist advice be obtained so that:

  • businesses understand the potential increased risks faced; and
  • where possible, contracts are updated so that appropriate protections are maintained.
Are there any other useful resources about apprenticeships during the coronavirus outbreak?

On 6 April 2020 the Government published further guidance to clarify the position with apprentices during the Covid-19 outbreak. The full guidance is available from here https://www.gov.uk/government/publications/coronavirus-covid-19-apprenticeship-programme-response/coronavirus-covid-19-guidance-for-apprentices-employers-training-providers-end-point-assessment-organisations-and-external-quality-assurance-pro

The guidance includes details of the measures implemented by the Education and Skills Funding Agency (ESFA) in order to provide flexibility in delivering apprenticeships in current circumstances. This includes breaks in learnings, delayed end point assessments and alternative arrangements for end point assessments. These measures apply immediately and until further notice.

There are a number of FAQs within the Government guidance which deal with common queries. The guidance contains some technical provisions and we recommend that you take advice if you are furloughing or making apprentices redundant. If you have any additional queries on the practicalities of implementing the ESFA measures please get in touch.

Further guidance changes to apprenticeships due to coronavirus can be found here.