Skip to content

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times

Related FAQs

Do I have to leave the UK to switch visas?

“Switching” is where you can transfer from one visa category to another without leaving the UK. However, in many instances where an individual wants to change from one visa category to another, they have to leave the UK and apply from the country they normally reside in.

There are currently limited concessions in place due to the pandemic where you are able to switch visas from within the UK instead of applying from overseas.  These are regularly updated and so please contact us for further information.

Which properties should I prioritise?

Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.

Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Will I have to go to court?

The vast majority of disputes settle without ever reaching a final hearing with something in the region of 2-5% of all cases actually ending up in court at a final trial.  So whilst it is very unlikely you would need to attend a court hearing, it is always a possibility.

When does Flexible Furlough start?

The Flexible Furlough Scheme was introduced from 1 July 2020 and is due to come to an end on 30 September 2021.