How do I guard against contractor insolvency in the construction industry?
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Almost two thirds of hearings conducted in the Civil Court will occur in person over the next few months as the Civil Court sees an influx in cases.
The Courts
In the Business & Property Courts, cases have been dealt with consistently since the start of the pandemic, except for trials that run for longer than 10 days in the Commercial & Admiralty Court. The Queen’s Bench Division and Administrative Court are also running as normal. If your case is listed for one of these courts, you do not need to be concerned that your case may take longer than anticipated, with conclusions still being reach at the normal rate.
Hearings
Since the start of the pandemic, most hearings have been conducted online through various platforms such as Skype for Business and Cloud Video Platform. The courts are of the view that remote hearings tend to take longer than those that are held in person. As a result, if your case is due to be held in person, the case may be heard in less time. HM Courts and Tribunals Service stated that:
“Wherever possible we will look to facilitate face-to-face hearings, but our expectation is that remote hearings will continue to play an important role for the foreseeable future, given that social distancing will continue to limit courtroom capacity compared to pre-Covid levels.”
More courtrooms have become available since the start of the pandemic, resulting in more facilities for cases to be heard in person, which will have the aim of helping to rid of the backlog of cases, along with remote hearings being conducted too, which is a welcome step forward.
Approximately 300 additional support staff will be employed for remote hearings before the end of 2020, enabling better service with remote hearings. The Government has decided that some civil judges will have the option to extend operating hours for cases to be held in the evenings and on weekends too, which may be most suitable for small and fast-track claims, resulting in a potentially faster outcome. The efficiency of all the new measures are being monitored and changes are being implemented, such as increasing the capacity of the Small Claims Mediation Service.
Small Claims Mediation Service
With claims of a lower value, a high proportion of cases successfully settle outside of court, therefore, if you have a small claim, the mediation service may be suitable for your case. Mediation involves a trained impartial third party, with the parties to the case discuss the dispute with the assistance of the third party, aiming to reach a settlement. Now with the increased capacity, it may make the mediation service more accessible, meaning that an agreement can be reached more swiftly rather than waiting for the matter proceed to a hearing.
The courts have stated that:
“We aim to increase capacity to accommodate 90% of parties who want mediation, rather than the current 40%. We are recruiting additional mediators and restructuring ways of working to achieve this.”
This is a positive shift for those with small and fast-track claims where legal costs ought to be kept to a minimum. Settling by mediation removes the need for trial costs, amongst other costs, and has additional benefits such as the matter being dealt with more amicably.
- Be alert to the fact that guidance on treating Covid-19 may change with emerging knowledge/scientific data and this may require subsequent modifications to treatment.
- Critical care staff should support healthcare professionals who do not routinely work in critical care but need to do so.
The Government has introduced new regulations, which took effect on 14 May 2020, to relax the publicity requirements in respect of planning applications.
Planning applications are usually required to be publicised by way of site notices and local newspaper notices and applications are to be made available for public inspection. The Government has recognised that these actions may not always be possible in accordance with social distancing guidelines and in order that Councils do not delay applications as a result of an inability to comply with the publicity requirements, the Government has relaxed the requirements.
A Local Planning Authority is now required to “take reasonable steps” to publicise a planning application, which may be through use of online newspapers, social media, or other electronic measures. What is considered reasonable will depend upon the circumstances of an individual application and will be proportionate to the scale and impact of the development. A large development that has previously generated significant interest will require more steps to bring the application to the attention of all of those with an interest than a householder application. The guidance emphasises the role of the publicity requirements, namely to enable those with an interest to make representations and to effectively participate in the decision making process and therefore community engagement remains key. It is recommended that the officer’s report refers to the steps taken where a Council has relied upon the temporary publicity arrangements.
The requirement to make planning applications available for public inspection has also been temporarily suspended providing that the applications are available for online inspection. In reality most LPAs already provide such an online facility. Where individuals are unable to access an application online LPAs should make alternative arrangements, for example providing information over the phone or providing a hard copy set of documents by post.
The regulations however only amend the statutory publicity requirements. In addition to these, all LPAs are required to have a Statement of Community Involvement which may provide for additional publicity requirements and the LPA will be bound by these regardless of the temporary relaxation of any statutory requirements. Where a Statement of Community Involvement does go beyond the statutory requirements, the Government guidance suggests that LPAs update these to ensure that local communities can continue to be consulted in the current climate.
The regulations are currently due to expire on 31 December 2020.
The definition of a relevant establishment is a question of fact for an Employment Tribunal. Guidance from case law says that ‘establishment’ should be interpreted very broadly (so as to avoid employers escaping the need to collectively consult), and may consist of:
- A distinct entity
- With a certain degree of permanence and stability
- Which is assigned to perform one or more tasks
- Which has a workforce, technical means and a certain organisational structure to allow it to do so
However, there is no need for it to have the following:
- Legal, economic, financial, administrative or technological autonomy
- A management which can independently effect collective redundancies
- Geographical separation from the other units and facilities of the undertaking