Skip to content

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved

Related FAQs

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What do I do if I have been endorsed for a Global Talent, Start-up or Innovator visa but my endorsement is due to expire?

Endorsing bodies are still processing applications for these visa types and endorsements are still being issued. You usually have to apply for your visa within 3 months of receipt of your endorsement. In most cases you will still be able to submit your application online within this timeframe however it will not be completed as visa application centres across the world are closed. If you cannot apply because you haven’t been able to travel and your endorsement has expired, you may still be eligible for a visa. You should make your application as planned and UKVI will consider all applications on a case by case basis.

What sort of issues are likely to have arisen?

The Coronavirus pandemic will have impacted businesses in many different ways, but some of the most likely impacts that could have a legal implication are as follows:

  • Services were not performed in accordance with contract during the period of disruption. This could be a reduction in volume of services performed, a suspension of services, or performance in a way that does not comply with contractual KPIs
  • Late delivery or non-delivery of goods because of factory closures, or disruption in the supply chain
  • Changes being agreed between parties to contracts to deal with the consequences of the Covid-19 outbreak
How may proceedings change after Covid-19?

During the COVID-19 global pandemic, trials and hearings have been mostly conducted over Skype for Business and various other online platforms. Looking forward to the future, what we have experienced during the lock-down may continue and we believe will make litigation a more streamlined, user friendly experience for litigants.

One example of a regime which has been introduced is hybrid trials for lower value claims. Hybrid trials allow for parties and their witnesses to be linked into the court room by video link, whilst the judge and advocates are present in court. This makes it easier and frees up more time for witnesses, which would otherwise be spent in travel and waiting time, especially for those with other commitments.

With hybrid trials, clients still get a full legal experience and the judge will still apply normal legal principles during the trial. The procedure for the case is the same, both leading up to the trial or hearing and during the case itself; except without the need to physically attend court. It may also mean that there will be less of a backlog arising from the current crisis with cases continuing to be heard, allowing for matters to be listed earlier and a quicker outcome for the parties involved.

The shift to the use of online platforms may prove more practical for all those involved in legal matters. Interim hearings can be heard remotely resulting in a time and cost saving for litigants. Even for the final hearing only the legal representatives need to attend court – again resulting in time and cost savings for all concerned.

Are permitted development rights now in existence for the creation of emergency medical facilities?

Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:

  • Preventing an emergency
  • Reducing, controlling or mitigating the effects of an emergency
  • Taking other action in connection with an emergency

It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.

The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.

Further detail of the permitted development right is available at the link below.

http://www.legislation.gov.uk/uksi/2020/412/made