Skip to content

How do EWS1 form requirements apply to leasehold flats sold to secure tenants exercising their Right to Buy under the Housing Act 1985 whether in low, medium or high rise blocks?

Where a lender requires a EWS1 as part of the mortgage requirements for a flat this will apply regardless of its tenure and will therefore apply to applicable RTB properties. It may also be required in order to obtain a valuation for the disposal notices and issues in obtaining it could cause problems in serving this within relevant deadlines required by legislation.

Related FAQs

My business has a contract with a public sector body – what guidance has the Government issued about payment under contracts between public and private sector bodies?

The Cabinet Office has published a helpful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). This can include making advance payments to suppliers, if necessary. The PPN sets out actions that public sector bodies should take (until at least 30 June 2020) to ensure continuity of service and to ensure that its suppliers can resume normal contract activity once able to.

The actions public sector bodies should be taking include:

  • Informing its suppliers (that they believe are at risk) that they will continue to be paid as normal until the end of June 2020 (even if service delivery is currently interrupted). Risk might include supply chains collapsing and/or significant financial implications for a supplier
  • If a contract involves a payment by results mechanism, basing payments on previous months (e.g. the average monthly payment over the previous 3 months), and
  • Ensuring that invoices submitted by suppliers are paid immediately to maintain cash flow in the supply chain and help to protect jobs.

If you are a supplier to a public sector body, you must act transparently and on an open-book basis, making cost data available to your public sector clients. You must also continue to pay your employees and subcontractors / suppliers. Suppliers to the public sector must not expect to make profits on any undelivered elements of a contract. The PPN makes clear that, should suppliers be found to be taking undue advantage, or failing to act transparently, a public sector body can take action to recover payments made to that supplier.

The PPN requires public sector bodies to urgently review their contract portfolios and take steps to support suppliers who they believe are “at risk”. However, no definition of “at risk” is given in the document.  We would suggest that if you are a supplier and you have yet to hear from a public sector client, you should seek to get in touch with them as soon as possible, particularly if you have concerns about your supply chain, staff retention and/or are experiencing financial difficulties currently. Given the requirement for transparency, you may be required to provide evidence, so it may be helpful to have any relevant documentation ready to send, if necessary, as this may help ensure a decision is made by the public sector client more promptly, particularly as the public sector body may have a number of contracts to consider.

 

How do I remain compliant and cover any risk?

Data on properties, and people, has never been more important.

Given that compliance is at risk here, such a decision must be made by the Board to ensure good governance. Board approval should be sought and recorded for the approach the organisation is taking.

It is essential that you continue to record your data on compliance and report to your board at all times, and that there is a clear audit trail for issues with access, and if appropriate to the Regulator. Access issues as a result of self-isolation should be readily identifiable.

Operatives need to be provided with the tools to operate in as safe a way as possible:

  • Checklist of questions to ascertain occupant’s current health
  • Protective equipment (masks, gloves, over clothing)

The Gas Safe website is a useful resource for updates: https://www.gassaferegister.co.uk/help-and-advice/covid-19-advice-and-guidance/

I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?

No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs