Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
Related FAQs
No, government advice remains that if employees can work from home, they should continue to do so in order to minimise social contact across the country in order to keep infection rates down.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.
PPN 01/20: Responding to COVID-19
The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.
This PPN provides guidance for the following circumstances:
- Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
- Direct award due to an absence of competition or protection of exclusive rights
- Call off from an existing framework agreement or dynamic purchasing system
- Call for competition using a standard procedure with accelerated timescales
- Extending or modifying a contract during its term
PPN 02/20: Supplier relief due to COVID-19
PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.
This PPN provides guidance for the following circumstances:
- Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
- Put in place appropriate payment measure to support supplier cash flow
- Where contract payments are based on ‘payment by results’ make payments based on previous invoices
- Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
- Ensure invoices submitted by suppliers are paid immediately on receipt
PPN 03/20: Use of Procurement Cards
The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.
This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:
- Increase a single transaction limit to £20,000 for key card holders
- Raise monthly limits on spending with procurement cards to £100,000 for key card holders
- Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs
Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.
The PPN also advises that by 30 April 2020, in scope organisations should:
- Ensure that a number of appropriate staff have the authority to use these cards
- Open all relevant categories of spend to enable these cards to be used more widely
The CMA sees only limited circumstances in which a full refund would not be given. The CMA accepts that where public health measures prevent a business from providing a service or the consumer from receiving it, the business may be able to deduct a contribution to the costs it has already incurred in relation to the specific contract in question.
This view reflects a relatively complex area of law under which parties are released from obligations under a contract if performance of that contract becomes impossible or illegal. This is called “frustration” of the contract. Under a law passed during World War II, a party to a contract that is frustrated who has incurred expenses is permitted, if the court thinks fit, to retain an amount up to the value of those expenses out of any money they have been paid by the other party.
The CMA’s view, however, is that this will not happen often, and that deductions from deposits will be limited.
Yes.
An employer which is aware that a worker or agency worker is or ought to be self-isolating, should not knowingly allow that worker or agency worker to leave the place that they are self-isolating in (“the designated place”). To do so without reasonable excuse would amount to an offence which could result in the employer being issued with a fixed penalty notice.
The value of the fixed penalty varies depending on if it is the first or subsequent fixed penalty notice to be issued:
| First fixed penalty notice | £1,000 |
| Second fixed penalty notice | £2,000 |
| Third fixed penalty notice | £4,000 |
| Fourth, and any subsequent fixed penalty notice | £10,000 |