Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
Parties still need to comply with the various Protocols that apply and will be expected to exchange information in the usual way. Court proceedings can be issued electronically.
There is not a magic number. It depends on the nature of the organisation, the work carried out, the organisational structure, the geographical spread, working patterns and conditions. We would give specific advice personalised to the organisation and taking all these and other factors in to consideration. There is no such things as too many MHFAs!
Most rent suspension clauses in commercial property leases are unlikely to come to the assistance of the tenant. These clauses normally apply only where the premises has suffered substantial physical damage and are, as a consequence, incapable of being occupied, used or accessed. The coronavirus pandemic does not involve any physical damage to a property, loss from the crisis will be purely financial. Such losses then will not be covered by the landlord’s buildings insurance policy in a way that will allow a tenant to claim rent suspension.