Skip to content

Do I need to give a personal guarantee to access finance under the Coronavirus Business Interruption Loan Scheme (CBILS)?

A number of our clients and networks raised issues in the early stages of the Scheme around the requirement for personal guarantees to access finance under the Scheme. The Scheme has now been updated so that:

  • For facilities under £250,000, personal guarantees cannot be taken to support lending under the Scheme.
  • For facilities above £250,000, personal guarantees may still be required by a lender but the amount which can be recovered under these guarantees is capped at a maximum of 20% of the outstanding balance of the CBILS facility after taking into account any other recoveries from business assets.

Related FAQs

What facilities are available under CBILS?

Lenders implementing the Scheme can assist in a number of ways, including:

  • Term loans
  • Overdrafts
  • Invoice finance
  • Asset finance facilities

The maximum value available under the scheme is £5m, with repayment terms of up to six years for term loans and asset finance. Overdrafts and invoice finance facilities will be available for up to three years.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Do you have to collectively consult for the minimum period of time before you can issue notice?

These periods are often mistakenly referred to as minimum lengths of consultation (especially by Trade Unions). That is not correct. Consultation can commence, conclude and notices of dismissal be issued within the 30 and 45 day periods. The expiry of the notice would just have to be outside of those restricted periods.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Do you think MHFA will become a legal requirement for businesses eventually?

This is something which is certainly on the Government’s radar as there is currently a Bill being heard in Parliament about making MHFAs a legal requirement for workplaces. It is still in the very early stages and therefore it is not clear at this stage what the outcome will be. What is clear is that this is an area which is being taken very seriously and it would not be surprising if measures were put in place regarding MHFAs in the workplace.