Do I need to dispute a Will before it goes to Probate?
It is always better for claims which challenge the validity of a Will to be brought before any Grant of Probate is issued because it is possible that distributions may have been made before your claim is raised, which can make recovery of assets more difficult.
In order to stop a grant being issued, a document known as a caveat can be lodged at the Probate Registry. This is often the first step in disputing the validity of a person’s Will, and it is a step which we can assist you with.
Related FAQs
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
It is clear that we are emerging from a completely unprecedented period of disruption for many businesses, and this may have had a huge impact on their contractual arrangements both with suppliers and customers.
As the lockdown eases, and we get back to business, it’s important that businesses take stock of what has happened, and ensure they review and address the legal and contractual consequences of what has been happening since the start of the global pandemic.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
This guidance from the Chief Coroner applies to reports of death and coroner investigations in England and Wales. It is to assist coroners in continuing to exercise their judicial decisions independently, in accordance with the law, and during the extraordinarily pressured events being faced at present.
In recognition of the problems that the current situation is causing, the UK IPO classed the 24th March and all subsequent days as “interrupted days” which means that deadlines that fall within this period will be extended until the UK IPO declares that the interrupted days have ceased. As lockdown has begun to be eased, the IPO has now reviewed its position and has confirmed that the “interrupted days” period will come to an end on the 29 July 2020. This means that Thursday 30 July 2020 will be the first normal day of operation, therefore all “interrupted days” deadlines will expire on this day. Similarly, if your deadline falls after the period of interruption ends, this deadline will not be automatically extended.
The IPO is conscious that many businesses may still be in challenging positions when the period of “interrupted days” end. They will endeavour to continue to provide flexibility and support to assist businesses with their applications. They hope to temporarily remove fees for requests for extensions of deadlines, and will give further updates when this fee exemption is in place.
The IPO continues to encourage applicants to meet original deadlines where they are able. As their offices are closed, the UK IPO is not currently processing paper forms (i.e. hard copy) and faxes. However, they are processing forms which have been submitted electronically, or via email and have made a new email address available for the submission of forms.
Intellectual Property Offices covering other territories have made their own announcements about the extension of deadlines. The EUIPO’s period of extension of deadlines came to an end on the 18th May. However, they have published a Guidance Note and accompanying webinar on the EUIPO website, detailing options for parties who may struggle to meet deadlines and remedies for those who may have missed deadlines.