Court proceedings have been issued. What happens to the court timetable?
The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:
- Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
- A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all
If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.
Even if the right to terminate the contract does exist, there might be particular rules about the following:
- How much notice has to be given
- How such notice has to be served (for example, it might have to be in writing to a particular address)
- When the notice can be served (perhaps on an anniversary of the start of the contract)
- How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)
All of these factors must be taken into account, and any contractual processes for termination are followed.
Every company has to file accounts at Companies House every year. If they are filed late, a fine is automatically levied. If there is a long delay in filing them, the directors are at risk of prosecution and the Registrar of Companies might start a process which could ultimately lead to the company being struck from the register.
However, Companies House has recognised that businesses might currently face exceptional problems in preparing and filing their accounts on time and so have posted a notice on their website which says that if immediately before the filing deadline, it becomes apparent that accounts will not be filed on time due to coronavirus, you can make an application to extend the period allowed for filing.
Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.
Many will have worked collaboratively with their suppliers and customers to deal with the immediate public health crisis. This will have meant offering flexibility as to contractual arrangements, whether in delivery dates, volumes of goods or services supplied, or even in the specification of what has been delivered.
If this is the case, it is important that businesses now do their legal housekeeping and make sure they have a proper record of what has been agreed. Unfortunately, our experience shows that many legal disputes arise out of amendments to contracts, typically where the parties to the contract each have a different view about what exactly they agreed to change.
We would therefore advise businesses to review any amendments that they might have agreed either verbally, by email, or otherwise, and consider whether they need to be captured in a more formal way which will make clear exactly what has been agreed to be varied, and (where appropriate) how long that variation will remain in force.
It’s also important to remember that some contracts contain provisions that set out specific requirements about how amendments are to be made. For example, they might require that amendments are made in writing (rather than verbally). These “No Oral Modification” clauses are commonly found in commercial contracts, and the courts have recently shown that they are willing to enforce them.
Failing to deal with amendments in accordance with contractual requirements could therefore have a serious impact on businesses as they recover from the disruption caused by the lockdown. If they end up in dispute with a customer or supplier, a business could find that the contract has not actually been amended in the way that they think – potentially leading to legal costs and liabilities at the worst possible time.