Skip to content

Can we still use the furlough (coronavirus job retention scheme)?

Yes. For further guidance, please see our FAQs section on Furlough.

Related FAQs

I pay child maintenance and half of my children's private school fees to my ex-partner but I have been placed on Furlough, with no top-up from my employer, so my income has dropped significantly. Is there anything I can do?

a. You should first try and discuss this with your ex-partner, either directly or through a Solicitor, to see whether an amicable agreement can be reached.

If you contribute to private school fees voluntarily, it is a matter for you and your ex-partner to resolve the issue with the school, depending whose name is on the bills. You may need to speak to the children’s school to see whether they can offer any reductions or remedies in relation to those payments. If you contribute to the school fees as part of a Court Order, you will need to ensure you do not breach the Order and you may need to consider applying for a variation of the Order if you can no longer afford the payments or reach a compromise agreement with your ex-partner.

You can use the Child Maintenance Service (CMS) calculator (https://www.gov.uk/calculate-child-maintenance) to recalculate your child maintenance obligations using your amended income. This recalculation can then be used in your discussions and you can formally instruct the CMS to verify that calculation if you and your ex-partner cannot reach an agreement about it. If you have already formally involved the CMS, they do carry out an annual review of child maintenance payments, however, they will also recalculate payments outside of the review period where there has been a change in income of 25% or more. We expect the CMS will be experiencing a high volume of enquiries at the present time so anticipate there may be delays in them assisting.

The position on child maintenance payments included in a Court Order are slightly more complicated and how you approach this will depend on how much time has passed since the date of the Order.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
I hold a licence but can’t trade. Can I terminate it?

A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.

Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.