Can we still use the furlough (coronavirus job retention scheme)?

Yes. For further guidance, please see our FAQs section on Furlough.

Related FAQs

Can I wait until April to carry out assessments?

We don’t recommend this. Status determination statements must be issued before 6 April 2021 for current engagements and the appropriate deductions are to be made on payments for services carried out on or after 6 April 2021.

How do I access the scheme?

Those who are eligible will be contacted directly by HMRC based on tax returns they have received. If you are eligible you will be asked to fill out an online application. HMRC will pay applicants directly.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Can landlords re-possess properties if tenants can’t afford to pay the rent because of the coronavirus outbreak?

After 25 March 2020, and until 30 September 2020, a landlord can only start possession proceedings against a tenant if they have served 3 months’ notice upon the tenant – irrespective of any grounds relied upon.

On 27 March 2020, the Court introduced new rules to put all possession proceedings (except against trespassers) on hold until 25 June 2020 – it means that the Court cannot make an order for possession or any other order that would cause someone to be evicted during that time.

These rules do not just apply to tenants who have fallen into rent arrears.

On 5 June 2020, the Government announced that this stay would be extended further until 23 August 2020.

This means that you can issue new possession proceedings (provided you have complied with the new temporary rules in relation to notice periods, if the notice was served since 25 March 2020) and you can continue with existing possession proceedings.

However, any progress you may be able to make in dealing with those proceedings is likely to be very limited – the Court will allow you to comply with directions orders that have already been made but non-compliance will not be punished (at least for the time being).

These rules, and the latest announcements, are in keeping with the Government’s expectation that landlords show compassion towards affected tenants and that all parties will work together to establish a suitable repayment plan to allow tenants to repay the arrears at an affordable rate.

What are the new Procurement Policy Notes (PPN)?

The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.

PPN 01/20: Responding to COVID-19

The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.

This PPN provides guidance for the following circumstances:

  • Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
  • Direct award due to an absence of competition or protection of exclusive rights
  • Call off from an existing framework agreement or dynamic purchasing system
  • Call for competition using a standard procedure with accelerated timescales
  • Extending or modifying a contract during its term

PPN 02/20: Supplier relief due to COVID-19

PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.

This PPN provides guidance for the following circumstances:

  • Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
  • Put in place appropriate payment measure to support supplier cash flow
  • Where contract payments are based on ‘payment by results’ make payments based on previous invoices
  • Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
  • Ensure invoices submitted by suppliers are paid immediately on receipt

PPN 03/20: Use of Procurement Cards

The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.

This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:

  • Increase a single transaction limit to £20,000 for key card holders
  • Raise monthly limits on spending with procurement cards to £100,000 for key card holders
  • Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs

Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.

The PPN also advises that by 30 April 2020, in scope organisations should:

  • Ensure that a number of appropriate staff have the authority to use these cards
  • Open all relevant categories of spend to enable these cards to be used more widely