Can I switch an existing loan facility onto the CBILS scheme?
If a business has been provided with a loan from 23 March on commercial terms, providing the borrower meets the CBILS eligibility criteria, lenders have been asked to bring these facilities onto CBILS wherever possible (e.g. where the lender is accredited to offer the same facility through CBILS) and changes retrospectively applied as necessary. Please contact us if this applies to you and we can review facilities and advise upon the potential changes that may be made retrospectively to the benefit of the business.
Related FAQs
This will be dependent upon the how the leasehold structure is set up for each relevant building, but it may be the local authority. We would be happy to provide further advice in relation to specific buildings if you contact us separately with the relevant details and documents.
The best advice is that parties should proceed as they would have done before the crisis began.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
You should speak to your advisors. We do not know presently how existing petitions will be dealt with by the Court. We do know that if any winding up order is made (based on a petition presented after 27 April), it could be found to be void and a creditor may face challenges. Even for petitions presented before 27th April, there is a risk that the Court will not be keen to make a winding up order so it is important that you look at the facts of your debt and weigh up all of the factors before deciding how to proceed.
There are two stages:
- Stage 1 – The provision of written information to the representatives.
- Stage 2 – Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters
Stage 1: Provision of information
The first stage in the collective consultation process is to provide the representatives with written information including details of the proposed redundancies (often called a section 188 letter). This information must be given to the appropriate representatives and the time limit before dismissals can take effect does not start to run until they have received it. It is this information which ‘starts the clock’.
It is possible that there will be changes to the proposals during the consultation process: indeed that is part of the reason for the process. The employer’s obligation is not just to provide the appropriate representatives with the relevant information at the start of the process. It is under a continuing obligation to provide them with information in writing about any developments during the consultation process (although later changes do not ‘restart the clock’ before dismissals can take effect).
Stage 2: Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters
The consultation process must include consultation “with a view to reaching agreement with the appropriate representatives” on ways of:
- Avoiding the dismissals
- Reducing the number of employees to be dismissed
- Mitigating the consequences of the dismissals