Are benefits to be included in the claim for a grant?
You cannot include the following payments in a claim:
- Discretionary bonus or commission payments
- Tips
- Non-cash payments
- Non-monetary benefits including taxable benefits in kind
- Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)
The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.
Related FAQs
The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.
Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.
The Office of the Public Guardian is continuing to accept applications to register Lasting Powers of Attorney but their usual estimated timescale of eight to ten weeks is likely to be affected by the current situation.
Consequently, an alternative or interim measure if you need something quickly is to execute a General Power of Attorney to authorise someone to act as your Attorney to undertake day to day financial transactions for you. The General Power of Appointment only needs to be executed by you in the presence of a witness (not the Attorney) to be valid and does not need to be registered with the Court of Protection. However, the Power of Attorney would cease to have effect if you become incapable of managing your affairs. It should be seen as a stop-gap only.
Potentially. The first question is why the person is not able to return, as their individual circumstances will be very relevant in terms of whether they can be safely dismissed.
Employers should ask themselves 2 questions in this situation:
- Have I done everything I am required to do in order to make the workplace safe for the individual to return; and
- Is what the employee saying reasonable?
If the answer to question 1. is no then a dismissal is unlikely to be fair. However, even if the answer to question 1. is yes, then there is still question 2. to address. If the employee has reasonable grounds as to why they are unable to return to work, e.g. due to health issues, childcare responsibilities etc then the dismissal is unlikely to be fair. It is only if you can answer yes to question 1. and no to question 2. that you can have some confidence in the potential safety of the dismissal.
Dismissals based on objections to returning to work on health and safety grounds will very often be risky and are highly fact specific, therefore please contact one of the employment team for further advice prior to dismissal.
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.